4
Commissioning
28
Festo – GDCP-CMMP-AS-M0-S1-EN – 1412a – English
4.3
Performance test, validation
Note
The STO function must be validated after the installation and after any modification to
the installation.
This validation must be documented by the person performing commissioning. To assist
you with the commissioning, questions for risk minimisation are summarised below in
the form of sample checklists.
The checklists below are no substitute for safety training.
No guarantee can be provided for the completeness of the checklist.
No.
Questions
Applicable
Com
pleted
1.
Were all operating conditions and interventions taken into
account?
Yes
0
No
0
0
2.
Has the “3-step method” for risk minimisation been applied, i. e.
1. Inherently safe design, 2. Technical and poss. additional
safety measures, 3. User information about the residual risk?
Yes
0
No
0
0
3.
Were the hazards eliminated or the hazard risk reduced as far as
practically possible?
Yes
0
No
0
0
4.
Can it be guaranteed that the implemented measures will not
pose new hazards?
Yes
0
No
0
0
5.
Have the users been adequately informed and warned about the
residual risks?
Yes
0
No
0
0
6.
Can it be guaranteed that the operators' working conditions
have not deteriorated due to the safety measures taken?
Yes
0
No
0
0
7.
Are the safety measures taken mutually compatible?
Yes
0
No
0
0
8.
Was adequate consideration given to the potential con
sequences of using a machine designed for commercial/indus
trial purposes in a non-commercial/industrial area?
Yes
0
No
0
0
9.
Can it be guaranteed that the implemented measures will not
severely impair the machine's ability to perform its function?
Yes
0
No
0
0
Tab. 4.2
Questions for validation in accordance with EN ISO 12100-1:2010 (example)