GB
7
Panel Removal
Before releasing the mounting brackets, disconnect the panel from the mains by double-
pole switch. Using tools, release erection bolts and lift the panel vertically upwards to
release the brackets from the screws. It is also necessary to disconnect the power supply
cable from the wall junction box.
Notice
Only a qualified person is allowed to work on the panel. The panel must be disconnected
from the power supply before starting any work. Because the natural marble is a delicate
material, it is necessary to be careful during transport, manipulation and montage. The
marble slab may only be cleaned with detergents which will not impair the surface quality
(polish).
Important Safety Instructions
Do not cover your heating unit in any way.
The "DO NOT COVER" warning tag is there
to remind you that any material covering the
unit can catch fire. Never place or hang any
furniture or curtains in front of the panel (see
Fig. 6) and ensure free air circulation.
Regularly, at least each time before starting a
heating season, clean the panel from dust.
Do not touch the panel from the bath/shower-
bath.
The panel may be mounted to the grounds of
flammability classes C1 and C2.
fig. 6
ATTENTION!
For first marble panel start-up is necessary to keep a starting temperature time as
is mentioned in table below in order to prevent marble stone desk cracking by
reason of very fast temperature increasing:
20 minutes Switch-ON
30 minutes Switch-OFF
30 minutes Switch-ON
30 minutes Switch-OFF