background image

 

6  

d)  Accelerating the warming of heating floors 

FOR HEATING MAT LAID IN A CONCRETE LAYER 

• 

Wait at least 4–6 weeks after installation before putting the 

mat into operation, so that the concrete will be set fully. 

• 

On the first day, set the temperature of the floor to be the 

same as the temperature in the room (maximum 18°C). 

• 

In the following days, increase the temperature in increments 
of 2°C per day up to 28°C. 

• 

Maintain the temperature of 28°C for three days.  

• 

Then, decrease the temperature of the floor by 5°C per day 

until you reach the initial temperature. 

• 

Afterwards, you can set the desired temperature and put the 

floor into normal operation. 

d)  Náběhy topných podlah 

ULOŽENÍ VE VRSTVĚ BETONU 

• 

Topná podlaha se uvádí do provozu až po řádném vytvrdnutí 
betonu po 4–6 týdnech. 

• 

První den nastavit teplotu podlahy shodnou s teplotou v 
místnosti (maximálně 18 °C). 

• 

Následující dny zvyšovat teplotu podlahy postupně o 2 °C/
den až na 28 °C. 

• 

Teplotu podlahy udržovat na teplotě 28 °C po dobu tří dnů. 

• 

Následně snižovat teplotu podlahy o 5 °C denně dokud 
nedosáhne počáteční teploty. 

• 

Poté je možno teplotu podlahy nastavit na požadovanou a 
uvést podlahu do běžného provozu. 

a)   Dimensioning / Dimenzování 

3. 

Moderate heating of piping to provide 

 

 

antifrost protection 

• 

The heating cables placed on metal or plastic pipes prevent 

liquid in the pipes from freezing when outside temperatures 
are below 0°C. 

• 

The  heating  cables  may  also  be  used  to  heat  or  maintain  a 

certain temperature in the pipes up to 60°C. 

3. Použití k protimrazové ochraně a k vyhřívání 

potrubí 

• 

Topné kabely umístěné na kovové nebo plastové potrubí 
poskytují ochranu před zamrzáním kapalin v potrubí při 
okolních teplotách nižších 0 °C. 

• 

Topné kabely lze taktéž použít na vyhřívání nebo udržování 
teploty v potrubí až do teploty 60 °C. 

Summary of Contents for MPSV 15

Page 1: ...odavatele stavby o um st n topn jednotky a o rizic ch z toho vypl vaj c ch Plocha mus b t po cel m obvodu odd lena od svisl ch konstrukc dilata n sp rou polystyren mirelon apod tl do 10mm The heating...

Page 2: ...ctures by an expansion joint polystyrene Mirelon etc up to 10 mm wide In case that cables are laid in an area larger than 20 m2 or with a diagonal greater than 7 m it is necessary to account for expan...

Page 3: ...ing system The installed output should correspond to a multiple of 1 1 to 1 3 times the calculated thermal loss due to the maximum recommended outputs see table below An additional heating device must...

Page 4: ...floor probe Instala n trubka s podlaho vou sondou 7 Finish floor N lapn vrstva b Installation system with moderate accumulation of heat INSTALLATION INTO CONCRETE self levelling screed Firstly read G...

Page 5: ...ojov n m m stnosti Prove te prom en odporu topn ho okruhu a izola n ho odporu zapi te do Z ru n ho listu Kabel zalijte vrstvou betonu do po adovan v ky po skon en beton sk ch prac op t prove te m en a...

Page 6: ...ch Prvn den nastavit teplotu podlahy shodnou s teplotou v m stnosti maxim ln 18 C N sleduj c dny zvy ovat teplotu podlahy postupn o 2 C den a na 28 C Teplotu podlahy udr ovat na teplot 28 C po dobu t...

Page 7: ...n mind that valves connections and flanges have greater thermal loss Therefore it is necessary to wind the cable in these parts in a closely spaced manner b Mont Topn kabely a senzor se mus k potrub p...

Page 8: ...ilable at the website http www fenixgroup cz 4 Z ruka reklamace Dodavatel kabelov ch okruh ECOFLOOR poskytuje z ruku na jej funk nost po dobu 24 m s c ode dne instalace potvrzen na z ru n m list insta...

Reviews: