700
2610 Ctrs
Ground
level
500 Ctrs
7
5
0
2690
Foundation 2 no. pads
900x400x200mm in
C20 concrete
(recommendation only)
175
200mm x M10
threaded rod
anchor resin
fixed into Ø14mm
hole
M10
S/S
cap nut
50
700 x 400 x 200mm
C20 Concrete Base
(recommended)
Ground level
Installation Instructions
ALL INSTALLATION WORKS TO BE CARRIED OUT BY COMPETENT PERSONNEL - INSTALL AS COMPLETE UNIT
Skop Table
(Surface Fix Only)
Skop Table
(surface fix only)
1. Install suitable foundation pads (see illustration) each with top face at ground level
2. Position table in correct orientation with bases centrally on foundation pads, then mark hole positions
through base plates.
3. Remove the table; drill holes Ø14mm x 175mm deep
4. Clear debris from holes.
5. Fill the holes to within approximately 35mm from the top with Hilti HY150 resin (or similar). Lift the seat (with
threaded anchor rods / capnuts in place) and carefully lower the anchors into the holes, leave for two hours
before using.
6. Using a torque wrench, tighten nuts and washers on to base frame to 30Nm to fasten down the table.
7. Check level
IMPORTANT NOTE:
Ensure that stainless steel is protected during site cutting of stone – contamination from disc cutters will
produce corrosion on stainless steel components.
Base Fixing Detail
4
SKOP TABLE installation