6 COMMISSIONING
Before starting to use the unit:
check that the tank, primary and secondary circuits are full or relevant fluids
check that the air has been removed from the circuits and that the relief valve is
properly closed
check that the pipes connected to the DHW circuit are connected properly
check all pipe connections for tightness
close
drain
cock
check
pressure(s)
in
expansion
vessel and
r
echarge if necessary
chock open P & T valve on top of tank (by fitting manual lever)
open
stopcock
and
fill
tank
with
water
until
if
freely
discharges
through
the
outlet
from
the
P
&
T
valve
remove chock and close P & T valve.
test
delivery
of
water
from
tank
by
opening
and
running all taps, both hot and cold
water and any other water discharges points (showers etc)
check
operation
of
expansion
relief
valve
on
Cold
Water Supply kit by lifting manual
release lever and discharging water
make sure that the electric wiring is made according to diagrams and instructions
check that there is no leakage
check that the voltage and frequency of the supply line is correct (see the unit label)
and that the earth connection is efficient
check the connection of other components, when present (thermostats, probes, etc.)
check that the pump runs properly, in case it’s blocked remove the plastic cover and
use a screw driver on the shaft to unlock it
if the pressure is less than 1 bar, add some water to the circuit
make sure all manual valves are in the open position
If any of the above listed checks fail, the unit MUST NOT BE OPERATED.
Only after having checked that all the checks gave a positive result the unit can be put in
function. According to the installation type, identify the operations to use to start the unit,
then:
apply electric power to the unit using the external switch
check that the Room Unit display powers on
check that the regulation components work properly
check that the storage tank temperature raises
check the correct operation of the safety thermostat (when present)
Note: Our technical personnel, who will visit when the ModuSat has been installed to
arrange for its final commissioning and calibration, do not perform the role of inspector
and/or approval officer for the system. Its compliance with standards and instructions
remains the exclusive responsibility of the installation company.
The ModuSat may have been transported and handled many times if you consider the on-
site storage, handling and installation, therefore it is vitally important that all unions and
connections are checked and tightened as required.
Summary of Contents for ModuSat FS 300
Page 32: ...32 3 6 ModuSat 300 dimensions...
Page 33: ...33 3 7 ModuSat 400 dimensions...
Page 43: ...43 5 3 Electric diagram ModuSat Standard...
Page 44: ...44 5 4 Electric diagram ModuSat Premier...
Page 45: ...45 5 5 Electric diagram ModuSat Premier...
Page 54: ...54 8 UK APPROVAL...