Instruction manual for SINLINE PRO 10000 series power supply units
2010/08/24
www.ever.eu
24
Figure 3: Connecting battery modules
Connecting modules
Note! When the safeguards are active, the voltage on the
connection terminals is dangerous to health and/or life. All
safeguards must be switched off before carrying out any
installation work!
1. Switch off the power supply unit by means of the user interface (CONTROL 1/3;
UPS).
2. Set fuses F3 and F4 to OFF.
3. Disconnect all battery safeguards (F1, F2 and F5) by opening the fusible cut-out
mounts. No specific order has to be observed. Remove the fuse-elements.
4. Disconnect all battery safeguards for already connected and newly connected
battery modules – to do this, open the fusible cut-out mounts and remove the
fuse-elements.
5. Disconnect the safeguards of the main line and the BYPASS in the room/building
switchboard.
6. Screw out the protective plugs of connecting elements (rear panel of the power
supply unit and modules).
7. Connect the module to the power supply unit, making sure to maintain the correct
polarity. The modules are connected in a row, i.e. connections are made between
the power supply unit and the first module, then between the first and second
modules, between the second and third modules, etc. The protective earthing
cables from each appliance are routed to a common point in the switching station
of the building.
8. Having checked the correctness of connections, secure the connecting elements
using the plugs. The cables should be secured against tearing out – to this end,
fix them with bands to the special grips located beneath the connectors.
9. Activate the safeguards in the switching station of the room/building.