Hypervolt ALM V1.0 – Setup Guide
1.
Introduction
The Hypervolt ALM has been designed with ease of installation in mind. Its lightning-fast reaction time to
overload currents coupled with the fact that Hypervolt records the power and energy from the CT means
you will improve on the safety of your installation while gaining insights into the energy usage of the
property.
2.
How it works
The Hypervolt works using a wired CT sensor which the installer must clip over the main incoming power
feed into the property. The Hypervolt CT is bidirectional meaning that the Hypervolt is able to differentiate
between export and import powers respectively.
Your property will have a maximum allowed total power consumption that can be configured inside your
Hypervolt. Once installed and configured, the charger monitors this consumption in real-time. In the event
that charging would cause you to exceed the pre-set limit, we will then reduce the EV charging rate in order
to protect your electrical wiring and avoid blowing the fuse in your meter whilst continuing to charge your
vehicle.
3.
Wiring and setting up
CAUTION:
make sure the Hypervolt is switched off and isolated from the mains before proceeding.
Connect the CT to the internal 2-pole signal connector provided inside the Hypervolt.
You must ensure the polarity of the CT is correct. The CT should be wired with the white lead into the left-
hand side terminal of the connector. The arrow on the CT should point in the direction of the load.
If you need to put the CT on the Neutral instead of the Live, the arrow on the CT should now
point opposite the load.