Instruction Manual ZHK
56/140
V07-21.0
Figure 103:
Sleeve
Figure 104:
Screwing
Figure 105:
Cable gland
A drill with the diameter for the corresponding gland diameter (see
, column 2) is sufficient
for the insertion of cables into a cabinet or a single walled housing. In this case the screw is locked
with the supplied locknut from the inside.
5.1.7 Transport lock
Remove the on fan-motor base frame of spring isolators mounted transport lock (signed with red
point) according to
below.
1. Remove nuts and bolts of position 1, 2 and 3
2. Remove z-shaped metal sheet (position 4)
3. Again fasten the nut of position 1, including the potential compensation wire
Figure 106:
Transport lock
5.1.8 Securing the position of AHUs
Floor AHUs must be fixed on the foundation to secure the position. A direct coupling see
left, should be avoided because of structure-borne sound transmission. If you use structure-
borne sound insulated underlayment, the fixing by lugs is particularly suitable to avoid the displace-
ment of the AHU in all directions (
1
2
3
4