5.
Terminate line (hot) to the Sense input.
a.
Locate the WAGO connector on the line (hot) wire (black) from the input labeled Sense.
b.
Run a line (hot) wire (typically brown, orange, or yellow) through conduit to a free
position on the WAGO connector.
c.
Lift up the orange clip, insert the line wire, and press the clip down onto the wire.
d.
Tug gently to make sure the wire is secure.
6.
Continue by connecting DMX (see
), then complete the
installation.
Complete Installation
1.
Check that all wires are terminated properly and secure in their terminals.
2.
Tuck wiring and WAGO connectors inside wiring compartment. Replace the wiring
compartment cover using the screws set aside previously.
3.
Rotate the fixture so it is roughly focused to its final resting position. This will assist in final
focus procedures.
Power Up Procedure
1.
Check that fixture power switch is on, if applicable.
2.
Check the DMX control source to ensure proper installation and termination per the
manufacturer's instructions.
3.
Apply power at the main circuit breaker.
After the power up procedure, the fixture will light.
Note:
All ArcSystem fixtures are factory set to provide 100% output level