COMMISSIONING
i) Remove both upper & lower locking grub screws from hinges using the 3/16” allan key provided.
ii) Using the same allan key, adjust either or both eccentric pins in each door hinge to level the door.
iii) Once the door is level, lock the eccentric pins in place using the locking grub screws.
Door
SIZES ARE APPROXIMATE ONLY. VARIATIONS MAY OCCUR IN MANUFACTURE.
3/16” Allan Key
Door Hinge
Eccentric
pin
Locking
grub screw
INSTALLATION
The cooker is supplied with the air intake at the front. If required the air intake can be taken from the rear
as follows:- (Fig. 7)
i) Remove the kicker plate securing screws.
ii) Remove the blanking plate located at the rear right-hand corner of the base. Fix the blanking plate over
the front primary air intake at the front right hand corner of the base.
iii) Replace the kicker plate.
Move the cooker into position. Connect water flow and return pipes. Remove left-hand panel and connect
oil supply. Fit electrical cables to the chosen system. Replace left-hand side panel. Fit the flue box. Make
the flue connection.
Fit the flue box sealing plate and gasket. Fit the flue box door (Fig. 8)
Fit the towel rail using the towel rail brackets supplied.
The baffle arrangement above the boiler heat exchanger need not be disturbed on installation.
If however, they have been removed for any reason, then they must only be replaced as shown in Fig. 9.
DOOR HINGE ADJUSTMENTS
Bypass
A bypass should be fitted. Where the water system can allow the boiler and pump to operate on bypass
only, the bypass must be placed at least 1.5m (5’3”) away from the boiler.
Inhibitor
Attention is drawn to the current issue of BS5449 and BS 7593 on the use of inhibitors in central heating
systems. If an inhibitor is to be used, contact an inhibitor manufacturer for their recommendations as to
the best product to use.
The water system and the electrical wiring system used must be in accordance with current regulations.
This appliance is fitted with two oil pressure jet type burners and must be commissioned by an
experienced pressure jet engineer (OFTEC) with the necessary equipment available for setting up the
burner and checking that combustion characteristics and chimney draught comply with those detailed in
the text.
Failure to comply will lead to incorrect operation, nuisance shutdown, equipment failure or damage to
appliance. GUARANTEE will be invalidated if the appliance is not correctly commissioned.
Procedure
Important:
Ensure the mains supply is isolated and that both thermostats are at the off position.
Remove control panel.
Check the oil and water connections for soundness.
Boiler Burner (Left Hand Burner)
Connect combined air bleed manifold and pressure gauge to pump.
Re-establish the electricity supply to the cooker.
Warning:
The power is now live. Extreme caution must be exercised.
Check that any ancillary controls e.g. room thermostat, programmer etc., are in an ON position.
Turn boiler thermostat to 80°C position. Burner should start ignition sequence.
(When the burner motor starts on a one pipe system it may be necessary to temporarily open the air bleed
screw on test manifold).