Instalacion_
124.fm -
17/5
/11
CLEVER02 Control panel
31
INSTALLATION
Turning direction check
1
Check the turning direction of the operator,
selecting dead man mode (DIP1=ON and DIP2=OFF)
and pressing A.T. (ST1, opening) and C.T. (ST2,
closing).
2
If the turning direction is not correct, interchange
the cables connected in cable connectors RL1 and
RL2.
Connection of safety transmitter-receiver photocells in closing (SG.C, FT2)
Connection of safety transmitter-receiver photocells in opening (SG.A, FT1)
Limit switches
O
The shutter gate stops at the end of the operation
by way of the FCA and FCC limit switches built into
the operator. It is therefore
necessary to always
have FCC and FCA and adjust them accordingly
.
We recommend installing opening and closing
safety photocells.
1
Complete the connections as shown in the figure.
O
If neither photocells nor a mechanical strip are
connected, make an electrical bridge between cable
connectors (5) GND and (6) FT2.
We recommend installing opening and closing
safety photocells.
1
Complete the connections as shown in the figure.
O
If neither photocells nor a mechanical strip are
connected, make an electrical bridge between cable
connectors (4) FT1 and (5) GND.
P124I
NO
1 2 3
(6) F
T2
(5) GND
(4) F
T1
(5) GND