Initial Installation
QUALIFIED INSTALLERS ONLY
A
DETAIL
A
SCALE
2 : 5
Step 1.
Remove cabinet holsters from either side of the unit
using a T-20 screwdriver. These parts are for packaging
purposes only and are no longer required.
Figure 19: Cabinet Holster Removal
Step 3.
Bend top standoffs by hand to form general shape.
Figure 22: Top Standoff Shape
A
DETAIL
A
SCALE
1 : 2
A
DETAIL
A
SCALE
1 : 2
Step 2.
There are four (4) nailing flanges to secure the unit to the framing, they are assembled flat from
the manufacturer. Remove the upper T-20 screw and rotate each nailing flange upward until
the bare nailing flange hole lines up and reinstall the T-20 screw. Bend the flange 90 degrees
making it flush with the cabinet face.
Figure 20: Nailing Flange Flat
Figure 21: Nailing Flange Assembled