Once the Tank Is placed in its final installation location and positioned properly, unscrew the bolts that fix the Metallic Pallet to
the Flanges of the Tank as per picture 6 above left and remove it as per picture 7 above in the middle. Then put the bolts back
in place screwing the flanges to the Tank as per picture 8 above on the right.
Pic. 6
Pic. 7
Place the Insulation of the Top of the Tank and the Top Cover as per picture 9 above left. Then Install the Flanges and Flange
Covers as per picture 10 above in the middle and finally install the plastic gaskets on the Flange Covers as per picture 11 above
right.
Pic. 10
Pic. 9
Pic. 8
Pic. 11