![ensto EVB100 Installation And Operation Instructions Manual Download Page 15](http://html1.mh-extra.com/html/ensto/evb100/evb100_installation-and-operation-instructions-manual_2414318015.webp)
15
RAK111_ENG / © Ensto 2019
Installation steps
1. Dig holes for cable conduits and the concrete
foundation to necessary depths.
2. Adjust the depth of the hole so that the top
of the foundation will be in level with the sur-
rounding ground surface. Note! Consider the
possible paving materials when setting the
level.
3. Cover the unused conduit openings with plugs,
which are included in the foundation delivery.
4. Lift the foundation into the installation hole,
the attachment bar embedded in the founda-
tion can be used as a lifting point. The attach-
ment bar should be oriented to allow attach-
ment of the Wallbox into desired position.
5. Lay the cable conduits into the trenches and
install conduits to relevant inlets.
6. Pull electric cables through the conduits into
the foundation approx. 1500mm measured
from the top of the foundation.
7.
Tighten the foundation to its place by filling
the excess space outside the foundation with
gravel.
8.
Set the final layer of gravel so that the top of
the foundation will be in level with ground or
the final paving material.
9. Always place a cover plate on the foundation,
if the Wallbox is installed in a separate session
than the foundation.
10. When you start the installation of the Wallbox,
remove the cover plate.
11. Put the adapter element on the foundation.
12. Attach the adapter on the foundation attach-
ment bar with bolts included in the delivery.
13. Fit the mounting pole to the threaded bolts on
the adapter. Secure with the nuts included in
the delivery.
14. Pull the electrical cables through the mounting
pole.
15. Attach the Wallbox on the mounting pole. See
instructions on page 16.
Ø115 (x4)
250
395
450
600
Ø15