7.Test Running
7.1 Key check project before test running
● Set all the terminal screws tight before running.
● Check all the connection of the terminal.
● Make sure no short circuit phenomenon.
7.2 Test running method
According to “Installation Guide”,make COM1 and WH short circuit;The system situation and
the light as follow table:
NO.
Light
System Situation
1
All the lights flash once
Power on
2
“POWER”light is on
System starts to self-check
3
“POWER + MPPT”light on
Pump starts to run
Remark
:
1
、
If water level sensors are not used,make COM1 and WH short circuit to run the
system.
8.Maintanance Method
8.1 Regular maintanance project
● Every panel’s output voltage is in normal range.
● The tightness of terminal screws.
● Check if there are any dust/iron scrap/mordant liquidin controller.
● Check if there are any noise or shaking of the pump when the system is on.
8.2 Attentions during the maintanance
●Disconnect the input power of controller before maintanance;
●The demounted metal spare parts are not allowed to put into controller,it will lead to open-
circuit of controller;
●Keep the controller clean after maintanance,avoid any dust or liquid invade into the
controller.
9. ERROR CODE AND MEANING
E001: Current Protection
E002
:
Voltage Protection
E003
:
Voltage Protection
E004: Tank Protection
E005: Tank Protection
E006: Tank Protection
E007: Tank Protection
E008: Low level Protection
E009: Low level+Current Protection
E010: Low level+Voltage Protection
E011: Low level+Voltage Protection
E012: Tank+Low level Protection
E013: Tank+Low level+Current Protection
E014: Tank+Low level+Voltage Protection
E015: Tank+Low level+Voltage Protection
E016: Data error
E032: Verify and Error
E064: Communications Blackout