background image

Step 2  Open Front Cover

 

4.  Loosen, but 

DO NOT REMOVE

 (2) lower nylock nuts on 

hinge bolts below burner. 

5.  Remove (3) upper nuts and support cover while opening. 
6.  Inspect burner head/end cone condition. 

 ANNUAL TUNE UP & INSPECTION 

 

 
 
 
 
 
 
 
 
 

 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 

 
 
 
 
 
 
 
 
 
 

 

 

 

 

Annual Tune Up and Inspection 

Ascent™ Combi & Ascent™     

Plus Combi Oil Boilers

 

Please refer to owner and installation manual for complete details. 

AIR BOX 

Step 5  Close Front Cover 

 

4.  Install (3) upper nuts and washers. 
5.  Tighten nuts (5) uniformly 

DO NOT overtighten. 

6.  Check and tighten (5) rear cover nuts. 
4.  Check Flue Pipe. 
5.  Check chimney base and clean if necessary. 

Step 3  Inspect Flue Passage and Vent System 

 

If passage is clean, no scale, then close cover and 
tighten all hardware evenly. 

Clean ONLY if dirty. 

Check vent system joints for proper connections, 
including Ascent Plus Combi flexible coupling clamps 
and condensate drain. 

Step 4  Clean Boiler 

 

Remove stainless steel alloy combustion chamber using caution, it may  
be hot. Brush and vacuum the heat exchange surface if needed. 

Step 1  Initial Test (Draft Check & CO

2

 

If there is an optional Silent Burner Cover, make sure it is in place 
before testing. 

 

1. 

Remove the 1/8” brass plug from the flue box plug (1) in the 
top right corner of the front cover. Check draft at the flue box 
(1) using a 12” long piece of ¼” O.D. steel or copper tubing 
inserted approximately 8” into the boiler.  Connect this tube to 
your test probe using a piece of hose. 

 

This must be negative for proper operation. 

 

 

2.  Check CO

through the “over fire” test port (2).  Insert the 12” 

long steel or copper tube approximately 8” in through the test 
port. 

 

Recommended settings at the test port:   
Oil-fired: 10% to 11% CO

2

 