4.   Insert the first CR123A camera type battery provided with your system into the 

battery cradle.  Then insert the second CR123A battery into its cradle.   

 

5. 

The sensor will have sent a “learning in” signal upon first power up and should now 
be programmed into position S4.  

6. 

If you have difficulty with this method you may alternatively depress the small round 
BLACK button inside the sensor.  This will “force” a learning signal only.   

 

 

 

7. 

Verify that the sensor is learned into place as indicated by a SOLID RED LED over    
position S4 on the Controller. 

8. 

Once the sensor has been learned in you will need to test the signal transmission.  
Please skip to section 6.4 TESTING YOUR SENSORS on page 40 of your Energy 
Eye Installation and Operations Manual.  PLEASE IGNORE POINTS 8 and 9 as 

they do not apply to the EE-IR-05 Sensor.  

9. 

After the sensor has been learned in, and the signal transmission has been verified 

you the jumpers located inside the PIR MUST be programmed.  By altering the 
jumper settings you will change the LED flashing patterns which greatly affects 
battery life.  During jumper programming always ignore the 7 prongs on the far 

edge of the sensor. 

a.  ECONOMICAL SETTING – This setting turns OFF all LED activity on 

the PIR.  This setting will yield the longest battery life for the sensor.  
REMOVE THE JUMPER MARKED “P3” and make sure the 3 
pronged jumper marked “P2” next to it is in the lower position (see 

following picture). 

Summary of Contents for IR-05

Page 1: ...UDING INTERFERENCE THAT MAY CAUSE UNDESIRED OPERATION NOTICE Changes or modifications not expressly approved by the party responsible for compliance could void the user s authority to operate the equi...

Page 2: ...assemble the product Doing so will void the Limited Warranty 6 USE ONLY APPROVED BATTERIES 7 The SENSOR should be installed by qualified personnel only 8 The Energy Eye receiver and sensors contain se...

Page 3: ...sensor has been designed with the same proprietary radio coding that is found in other high quality Energy Eye wireless components and will not interfere with other sensors or wireless devices within...

Page 4: ...tern of coverage Avoid installing 2 PIR detectors in one room protecting the same area Like all Energy Eye wireless components PIR should be less than 30 feet 10 meters from Controller Unit Optimal PI...

Page 5: ...of this User Manual 1 Remove PIR sensor from its original packaging or container Use the supplied anchors and screws mount the base plate to the ceiling If the ceiling is made from Concrete it may be...

Page 6: ...LE 1 Depress and hold the LEARN button while pressing the S4 TACT button THREE 3 TIMES then release You will notice the RED LED above position S4 flashing very slowly 2 The Controller is now looking f...

Page 7: ...nal transmission Please skip to section 6 4 TESTING YOUR SENSORS on page 40 of yourEnergy Eye Installation and Operations Manual PLEASE IGNORE POINTS 8 and 9 as they do not apply to the EE IR 05 Senso...

Page 8: ...ion of a typical guestroom smoke detector To activate this setting leave jumper P3 in place and make sure jumper P2 is in the lower position see following picture c LED INDICATION TEST SETTING This se...

Page 9: ...Toll Free 1 866 463 3135 Ph 01 858 202 0001 Fax 01 858 202 0008 Web www energy eye com Email info energy eye com NOTES ____________________________________________________ ____________________________...

Reviews: