Commissioning
30
4.
Switch the P2 reagent pump "on" (with
F
select P2 and with
V
set to "g") and leave it running
until you can tell that there are reagents at the Tconnector. After this, switch P2 "off" (s) with
W
.
5.
Now switch the valves to passage for standard (select V1: S, V2: S; with
F
or
K
switch to "S"
with
V
) and then switch the P1 sample pump "on". Leave the pump running until you can tell
that there is standard at the T-connector. Switch P1 back "off".
6.
Now switch the valves to passage for cleaning agent (select V1: S, V2: R; with
F
or
K
switch
to "R" or "S" with
V
) and then switch the P1 sample pump "on". Leave the pump running until
you can tell that there is cleaning agent at the T-connector. Switch P1 back "off".
7.
Now switch the valves to passage for sample (select V1: P, V2: S; with
F
or
K
switch to "P"
or "S" with
V
) and then switch the P1 sample pump "on". If you can tell that there is sample
at the Tconnector, leave the pump running for another 2 minutes. This removes any remains
of standard or cleaning agent.
Then switch P1 "off".
!
Note!
For the two-channel version, valve V3 must be set additionally for switch-over between channel 1
and channel 2.
8.
Now proceed as with dry commissioning (from step 2).