Proline t-mass 65 PROFIBUS DP/PA
Commissioning
Hauser
49
7
Commissioning
7.1
Function check
Perform all the final checks before putting the measuring point into operation:
• Checklist for "Post-installation check"
• Checklist for "Post-connection check"
7.2
Switching on the measuring device
Only switch on the supply voltage once all the final checks have been performed. The mea-
suring device is now operational.
The measuring device performs a number of power on self-tests. As this procedure pro-
gresses the following sequence of messages appears on the local display:
Normal measuring mode commences as soon as start-up completes.
Various measured values and/or status variables appear on the display (HOME position).
!
Note!
If start-up fails, an error message indicating the cause is displayed.
7.3
Quick Setup
All important device parameters for standard operation can be configured quickly and easily
by means of the Quick Setup menu, especially for devices that have been delivered with fac-
tory default settings.
!
Note!
If the measuring device has been ordered with customer-specific settings then the Quick
Setup is not necessary. Check that the parameterization protocol on the CD delivered with
the device matches your required data.
t-mass 65
START-UP
Start-up message
t
DEVICE SOFTWARE
V XX.XX.XX
Current software version
t
SYSTEM OK
OPERATION
Beginning of normal measuring mode
t