Commissioning
TMT162 HART
28
Hauser
4
Commissioning
4.1
Function check
Prior to commissioning, please ensure that:
• The device has been mounted correctly
• The electrical connection is correct
4.2
Switching on the device
Once the final checks have been successfully completed, it is time to switch on the supply
voltage. The device is ready for operation after approx. 18 seconds!
Normal measuring mode commences as soon as the switch-on procedure is completed. Various
measured value and/or status variables appear on the display.
4.3
Display and operating elements
4.3.1
Display
T09-TMT142ZZ-07-00-00-xx-001
Fig. 8: LC display of the field transmitter (illuminated, can be plugged in in 90° steps)
°C
°F %
K
10
0
20
30
40
50
60
70
80
90
100
!
Ê
Ë
Ì
Í
Î
Ï
Ð
Summary of Contents for iTEMP TMT162
Page 2: ......
Page 45: ...TMT162 HART Endress Hauser 45...
Page 46: ...TMT162 HART 46 Endress Hauser...
Page 47: ...TMT162 HART Endress Hauser 47...
Page 48: ...www endress com worldwide KA250R 09 a3 01 10 71042473 FM SGML6 0...