This installation guide gives instructions for the replacement of the pressure transducer placed on the liquid receiver 
on Copeland  EazyCool

™ CO

2

 refrigeration units. The PT5 replacement kit makes it possible  to install a  pressure 

transducer into the compressor compartment of the CO

2

 unit, instead of the flashtank shut-off valve  where it  was 

placed originally. This installation guide describes the main working steps and provides some useful tips. 

Main steps 

1. 

Switch off the main switch to shut the unit down. 

2. 

Isolate the unit from the cooling circuit by closing the shut-off valve on compressor discharge and the shut-off 
valve on flashtank. 

3. 

Remove  pressure  (charge)  from  the  liquid  receiver  of  the  unit  including  the  whole  discharge  line  and  the 
gascooler. 

4. 

Install the PT5 kit as per instructions below. 

5. 

Switch on the main switch. 

6. 

Check the functioning of the new pressure transducer on the visograph display. 

7. 

Perform a leakage test. 

8. 

Insulate the Schraeder connection as per instructions below. 

9. 

Put the device into operation. 

Kit contents 

A.  Brazed set including PT5 pressure transducer, high-pressure hose and rubber stepper plug 
B.  Bracket 
C.  Plastic clamp Ø 19 mm 
D.  Fasteners 
E.  Plug 1/4" NPT 
F. 

Copper seal to high-pressure hose 

G.  Insulation set (insulation pipe and insulation tape) 

 

Figure 1

 

Summary of Contents for COPELAND EAZYCOOL

Page 1: ...eps 1 Switch off the main switch to shut the unit down 2 Isolate the unit from the cooling circuit by closing the shut off valve on compressor discharge and the shut off valve on flashtank 3 Remove pressure charge from the liquid receiver of the unit including the whole discharge line and the gascooler 4 Install the PT5 kit as per instructions below 5 Switch on the main switch 6 Check the function...

Page 2: ...om the old pressure transducer and remove the PT5 from the port of the shut off valve Use a 1 4 NPT plug E with sealing glue Loctite to blind the shut off port Tighten the 1 4 NPT plug E to a tightening torque of 40 Nm 2 Remove the plastic plug from the metal partition wall 3 Remove the currently used plug on the Schraeder valve SAE 1 4 on the shut off valve Figure 2 1 2 3 ...

Page 3: ...artment area in Figure 4 2 Pull the cable of the old pressure transducer through the hole in the partition wall into the compressor compartment area see result in compressor compartment area in Figure 4 3 Blind the partition wall with the rubber stepper plug on the brazed set 4 Install the assembly bracket for the brazed set Key 13 mm see Figure 4 Figure 3 Figure 4 Compressor compartment area and ...

Page 4: ...different versions with the holes located in different positions Figure 5 Figure 6 6 Connect the high pressure hose with the Schraeder port on the shut off valve of the liquid receiver as per Figure 7 Use the copper seal F The high pressure hose must be placed freely so that the Schraeder connection is not strained The Schraeder connection must be tightened to a torque of 16 to 18 Nm Do not exceed...

Page 5: ..._CO2_PT5 E Rev00 5 5 7 After leak test has been performed insulate the Schraeder connection including the angle fitting of the high pressure hose using the insulation set G see Figures 8 and 9 Figure 8 Figure 9 ...

Reviews: