Place tape measure at the end of the top tube
(riser collar) and measure down to distance E.
Carefully cut the drop tube to the required
length. Use a hacksaw equipped with a fine
tooth blade to ensure a straight 90-degree cut. 

An angled cut is permissable, but the 4”-6” dis-
tance from the bottom of the tank must corre-
spond to the top of the cut as shown.

Spill
Containment

Tape Measure

Riser Pipe

Figure 4

E

D

20. Remove all metal chips or debris left from cutting or drilling. Shake the

A1100EVR overfill prevention valve in a vertical position. Verify that the
A1100EVR drop tube o-ring is installed properly. Locate the A1100EVR
overfill prevention valve over the tank fill riser opening with the A1100EVR
collar pointing upward. Carefully lower the A1100EVR overfill prevention
valve into the tank until the A1100EVR collar is resting on the riser pipe.

21. Install warning plate on the riser using the hose clamp provided.

A1100EVR Overfill Prevention Valve Top Drop Tube Cut Length

1.

Find measurement A, the distance from the inside top of the tank to the top
edge of the riser pipe as shown in Figure 1.
If the tank has a manway (Figure 3), make sure to include the height of the

 

manway

 

when finding measurement A as shown in Figure 2, A = J + H .

 

Consult your tank diagram to determine the proper H dimension. If this

 

dimension cannot be found, use 6” as the H dimension (typical manway

 

height is 5”-7”).

When installing the A1100EVR overfill prevention valve below the spill

 

containment drain valve, measurement A is the distance between the inside

 

top of the tank to the top edge of the A1100EVR overfill prevention valve 
seat as shown in Figure 2.

7

Tape Measure

Riser Pipe

Maximum
Fluid Level

Spill
Containment

Containment
Nipple

Figure 1

B

A

A1100EVR Overfill Prevention Valve Installed Above Drain Valve

Conventional, Non-EVR Application

19.

Bottom Tube Cut Location, Measurement E:

Find measurement D, the distance between the
top of the riser pipe and the bottom of the tank
as shown in Figure 3.
PEI Recommended Practice suggests 4”-6”.

Cut Length E = D - 5”

A1100EVR Overfill Prevention Valve to Tank Fill Riser 

Figure 2

Maximum
Fluid Level

Riser Pipe

B

A

A1100EVR
Seat

A1100EVR Overfill Prevention Valve Installed Below Drain Valve

EVR Application

Top of
angled cut

Bottom of
tank

4”-6”

4”-6”

C

C

IMPORTANT: Do not use a power saw, pipe or tubing cutter as this may
result in damage to the bottom of the lower drop tube, voiding warranty.

2

Summary of Contents for A1100EVR GUARDIAN

Page 1: ...ation of the A1100EVR overfill prevention valve 3 Never disconnect the delivery elbow from the fill adapter when the A1100EVR overfill prevention valve has reached the positive shut off point of 95 total capacity Note the tank delivery hose is full and must not be dis connected until enough fuel has been evacuated from the underground stor age tank This will allow the tank delivery hose to drain a...

Page 2: ...7 t ...

Page 3: ...it tank fill to 95 95 Shut off Tank Diameter B Dimension Feet Meters Inches mm 6 5 1 98 7 5 190 7 0 2 13 8 0 203 7 6 2 29 9 0 229 8 0 2 44 9 5 241 8 2 2 50 9 5 241 8 5 2 59 10 0 254 9 0 2 74 10 5 267 9 5 2 90 11 0 279 10 0 3 05 11 5 292 12 0 3 66 14 0 336 IMPORTANT The A1100EVR overfill prevention valve is not recommended for tanks under 6 5 feet in diameter 3 Top Tube Cut Location Measurement C A...

Page 4: ...5 ...

Page 5: ...100EVR collar inside the top end of the drop tube and align the four holes 12 Using the indenter tool and a hammer apply a sharp blow to counter sink each individual hole before attempting to install the mounting rivets 13 Using only the factory supplied rivets apply a good amount of the Seals All Sealant around the base of each rivet before installing into each of the four holes Using the rivet g...

Page 6: ...3 ...

Page 7: ... is installed properly Locate the A1100EVR overfill prevention valve over the tank fill riser opening with the A1100EVR collar pointing upward Carefully lower the A1100EVR overfill prevention valve into the tank until the A1100EVR collar is resting on the riser pipe 21 Install warning plate on the riser using the hose clamp provided e 7 19 Bottom Tube Cut Location Measurement E Find measurement D ...

Page 8: ...N 26 6 e d ...

Reviews: