About this guide

This guide describes how to install a new EMC Isilon node.
You can follow the procedure in this guide to:

l

Install several nodes to create a new cluster.

l

Add a new node to an existing cluster.

The installation procedure is the same whether you are creating a new cluster or adding a
node to an existing cluster. When you reach the step where you configure the node, you
will select whether you are creating a new cluster or adding a node to an existing cluster.

Note

If you are installing multiple nodes, repeat this procedure for each node. Power up each
node individually before installing the next node.

Drive types

This procedure applies to nodes that contain any of the following drive types: self-
encrypting drives (SEDs), hard disk drives (HDDs), and solid state drives (SSDs).
If you are performing this procedure with a node containing SSDs, follow the additional
steps provided in this document to ensure compatibility with the cluster.
If you are performing this procedure with a node containing SEDs, the node might take up
to two hours longer to join the cluster than a node with standard drives. Do not power
down the node during the join process.

Confirm SSD compatibility

If you are installing a new solid state drive (SSD) into a cluster, you must confirm that the
drive you have onsite is compatible with the cluster.

See the 

Isilon Supportability and Compatibility Guide

 to determine whether the drive you

have is compatible with the cluster.

Unpack and verify components

Before you install any equipment, inspect it to make sure that no damage occurred during
transit.
Procedure

1. Remove the node components from the shipping package and inspect the

components for any sign of damage. If the components appear damaged in any way,
notify Isilon Technical Support. Do not use a damaged component.

Note

To avoid personal injury or damage to the hardware, always use two people to lift and
move nodes.

Installation Guide

2

NL400

  

Installation Guide

Summary of Contents for Isilon NL400

Page 1: ...d verify components 2 l Install the node in a rack 3 l Install the drives in the node 6 l Install the front panel 9 l Back panel 10 l Connect the internal cluster network 10 l Connect the external cli...

Page 2: ...teps provided in this document to ensure compatibility with the cluster If you are performing this procedure with a node containing SEDs the node might take up to two hours longer to join the cluster...

Page 3: ...ed components Four 8 32 0 75 inch knurled slide rail mounting screws Secures the slide rails to the rack cabinet Eight 8 32 0 25 inch shoulder alignment pins Use only for a pre threaded rack cabinet E...

Page 4: ...mbled step alignment pins in the ends of the outer rails with the proper shoulder alignment pins Mount the outer rails Mount the outer rails in the rack cabinet Procedure 1 Adjust the outer rail rear...

Page 5: ...y extend each intermediate rail until the rail locks into place 1 2 1 Inner Slide Rail 2 Intermediate Slide Rail 2 Keep the node level with the rails and align the ends of the inner rails with the end...

Page 6: ...lead to severe injury when the node is pulled for future maintenance Install the drives in the node After the node is secured in the rack install the drives in the node There are 36 drive bays that yo...

Page 7: ...eated will not be recognized when the node starts and a red light will appear below the drive To avoid this error run your finger across all the installed drives to ensure that they are seated evenly...

Page 8: ...ar EMI shield 5 Insert and lock drives into the back bays until they are full 1 2 3 1 Rear EMI shield 2 Locking handle 3 Drive bay 6 Replace the rear EMI shield Installation Guide 8 NL400 Installation...

Page 9: ...ays status information You can use the keypad and LCD to perform basic configuration tasks Procedure 1 Install the front panel assembly by aligning the front panel with the front of the node and then...

Page 10: ...irect access to the node connect to the serial port LEDs Do not rely on LEDs to determine the health of a node or node component If any hardware component is in an error state identify and troubleshoo...

Page 11: ...the node to the switch for the external network For additional 1 Gb connections use the ext 2 port CAUTION You must connect the 1 Gb ext 1 port to the external network even if you were planning on on...

Page 12: ...power is present Note Both power supplies must be connected Operating a node using only one power supply for an extended period will shorten the life of the power supply If the installation site has...

Page 13: ...e mode is incompatible with Isilon for vCenter VMware vSphere API for Storage Awareness VASA and the VMware vSphere API for Array Integration VAAI NAS Plug In for Isilon Connect to the node using a se...

Page 14: ...le you to disable SmartLock compliance mode This is the last opportunity to back out of compliance mode without reformatting the node 2 Follow the prompts to configure the node For new clusters the fo...

Page 15: ...You can configure the external network with IPv6 addresses by entering an integer less than 128 for the netmask value The standard external netmask value for IPv6 addresses is 64 If you enter a netma...

Page 16: ...ing menus The LCD screen will be dark until you activate it To activate the LCD screen and view the menu press the square selection button You can press the right arrow button to move to the next leve...

Page 17: ...the node with the right and left navigation buttons You can view the drives in other nodes in the cluster with the up and down navigation buttons The node you are viewing will display above the drive...

Page 18: ...can press the left navigation button to back out of this menu without shutting down or rebooting Update the install database After all work is complete update the install database Procedure 1 Browse...

Page 19: ...and user contributed content into topic areas making it easy to find content about subjects that interest you Support for IsilonSD Edge If you are running a free version of IsilonSD Edge community sup...

Page 20: ...ublication and specifically disclaims implied warranties of merchantability or fitness for a particular purpose Use copying and distribution of any EMC software described in this publication requires...

Reviews: