background image

2-4

3-4

Before  filling  filters  with  sand  or  other  filtration  elements,  it  is  advisable  to  check  the  internal 
collectors to make sure that they have not been damaged during transport or installation. 
Afterwards, fill the filters with water and make hydraulic test. Thus, you will make sure that there is 
no leak and that the equipment works properly.
Then stop the pumps, open each filter's lid (the filter must not be emptied without opening the lid, 
as it could collapse) and empty half the water that each filter contains. Then, start filling the filter 
with sand or other filtration elements, taking into account that first of all you must put gravel up to 
the collector arms (10 cm approx.)
This  must  be  done  very  carefully  in  order  to  avoid  any  damage  in  the  lower  components  of  the 
filter. When the filter is being filled with sand, this must be carefully spread over the surface.
Once  the  filter  is  full  with  the  filtration  elements  clean  the  lid  and  the  inner  part  of  the  manhole. 
This will prevent any debris and particles of sand affecting the seal of the joint.

Introduce  the  lid  in  the  manhole,  leaving  it  leveled  and  centered.  The  lid  must  be  supported  by 
the handle, as this will avoid that it could fall into the tank and damage any of its parts.
Put the bridge in the position shown and tighten manually the wheel.
To achieve a proper seal, you do not have to tighten excessively the wheel, as this could damage 
the lid. The pressure itself will improve the seal.
When  the  filter  is  under  pressure,  it  is  normal  that  wheel  and  bridge  remain  separated.  You  must 
not tighten the wheel again when the filter is under pressure, because when the pumps stop, the 
lid could be damaged or blocked.

Once  the  filter  has  been  completely  filled  with  water,  start  the  performance  of  installation, 
venting  manually  to  eliminate  all  the  air  that  could  be  inside  the  filter,  as  the  presence  of  air 
impairs the filter performance.
If a vacuum forms in the filters, it is necessary to install double effect suction cups, these will also 
act as automatic air purifiers and would avoid that the tank could collapse.
After this, the filter has been ready for working process.

1.1) 

It is acceptable to place the filters under the water level.
However if vacuum occurs in the installation, suction cups must be installed in the lids to avoid that 
depression could collapse the filter's tanks.
Filters must be situated so that their bases are perfectly level and completely supported by the floor.
The location must be of appropriate size to allow maintenance periodic overhauls and other 
w o r k . Additionally the room must provide a drain to allow, in case of accident, evacuation of water 
flowing from any tube, filter, pump, etc. this will avoid risk of damages in the electrical installations 
(pumps, electric panels, etc.)

1.2) 

The manometer panel had been installed in the filter. In pools filters, the usual pressures when the 
filter is clean are:

2

·

 Inlet pressure: 0.8-1 Kg/cm .

2

·

 Outlet pressure: 0.4-0.6 Kg/cm .

2

When  the differential pressure between the two manometers is 1 Kg/cm  or higher, backwash 
must be carried out.

Filters location.

Manometers.

INSTALLATION

STARTING

INNER PART OF

MANHOLE

HANDLE

BRIDGE

WHEEL

LID

1) Filter installation

Filters are delivered properly packed and ready in order to 

facilitate unloading and transport using fork-lift truck, 
crane, etc. It is very important to make sure that the filters 
have not suffered bumps during transport.

To obtain a correct filter installation, the following stages must 

be observed:

· 

 Install filters in their final location.

· 

 Install correctly the butterfly valves in the filters.

· 

 To connect with the flange of the filter, use PN1.6MPa or 

Class E 15bar PVC pipe.

· 

 Install butterfly valves supports and regulate them correctly 

(height, etc.)

· 

 Connect butterfly valves with the pipe of the pumps, return 

pipes and drain.

· 

 Check the inner parts of each filter (collectors, top 

diffusers). 

· 

  Fill the filters with water.

· 

  Empty half the water and add the filtration element 

(gravel, sand and/or anthracite), etc.

Instrument Panel installation:

· 

  Before running the filter, drill a Φ11.4 diameter hole in the 

filter's return pipe and drain that connects  to the water 
inlet and outlet.(Figure 1, Figure 2)

· 

  Tap a 1/4" thread to the hole with Teflon tape. (Figure 3, 

Figure 4)

· 

  Twine the connection head with Teflon tape, fix to 1/4" 

thread and connect to the direct head and the valve of 
the panel.(Figure 5, Figure 6, Figure 7)

Caution:

· 

  Tap with PN1.6Mpa or Class E 15bar PVC pipe.

Figure 1   

Figure 2   

Figure 3   

Figure 4   

Figure 5   

Figure 6   

Figure 7   

INLET

OUTLET

Reviews: