COMMISSIONING
35/56
EN
5 .7
Commissioning record
Confirm the work carried out in the commissioning report below by marking and X or an
✓
.
Commissioning work
Note
Done
Check the heating system has been filled
correctly and the air has been removed
Check the flue system
Check there are no leaks in the fuel supply
system
Start the burner and check that it is operating
normally
Measure the parameters of the combustion
system and record all the main data pertaining
to the first ignition
Explain to the proprietor and person
responsible for the domestic heating system
the burner is installed on, the importance of
ensuring good inflow of combustion air and
combustion product evacuation. They should
also highlight that no modification should be
made to the heating system (comprised of air
intake, burner, boiler and flue pipe) that could
alter the correct operation of the system
Confirmation of correct commissioning:
Stamp / date / company signature:
______________________________________________