4.1
START-UP SEQUENCE
The purpose of the start-up sequence is to synchronise all the installed elements (generator, control panel,
lighting).
Once this sequence has been run, all the functions of your Hammam/Turkish bath will be easy to run from the
control panel.
The start-up sequence must be run the first time the AQUASTEAM MAXI steam generator is run up.
You only need to run the start-up sequence for the AQUASTEAM/EASYSTEAM models if an external control
panel or light fitting is added.
Please note that the start-up sequence need only be repeated after additional optional EFFEGIBI features
have been added at a later date.
Make sure that the steam generator is connected to the electricity and water supplies.
If there is also a second optional external panel, the start-up sequence must only be run from the
Aquasteam/Aquasteam Maxi/Easysteam steam generator.
Switch on the panel by pressing the “ON/OFF” button (
fig. A
).
fig. A
Press the temperature controls, buttons “C” and “A”, firmly and in rapid succession, and they will glow
brighter, and then the “ON/OFF” button. In
fig. C
, the sequence is shown as numbers “1”, “2” and “3”.
The “ON/OFF” button (shown as number “3”) must be pressed firmly for a few seconds until all the control
panel buttons have been flashing.
fig. B
The panel will display all the icons with a dimmer light. The control icons will flash, buttons “B” and “C” and
the Effegibi logo will appear with a brighter light (see
fig. B
).