INSTALLATION

 

All matters for installing the EFAPOWER EV-QC45 are described in this chapter. 

5.1

 

ENVIRONMENTAL REQUIREMENTS 

EFAPOWER EV-QC45 reliability is dependent upon compliance of environmental specifications. The design of the 
environmental control system for your EFAPOWER EV-QC45, in case of extreme environmental conditions, must 
ensure that the Unit can operate reliably while remaining within the range of its operating specifications. 

5.1.1

 

LOCAL CONDITIONS 

 

 

The installation of EFAPOWER EV-QC45 shall not be made in a commercial garage (repair facility) or 
closer than 6,1m (20 feet) of an outdoor motor fuel dispensing device. 

EFAPOWER EV-QC45 is in an IP54, IK10 (NEMA 3R) enclosure. This Unit is intended to work below 50ᵒC (122ᵒF) 

ambient temperature. 
 

Clearance around the cabinet 

The  air  must  circulate  freely  throughout  the  ventilation  grids  in  order  for 

the  charger’s  cooling  system  to  be 

effective.  The  ventilation  areas  on  the  sides  and  back  must  not  be  blocked,  assuring  that  the  Quick  Charger 

cooling  system  can  be  effective.  Efacec  recommends  clearance  of  at  least  1meter  (40’’)  in  the  front  (HMI 

interfa

ce) and on right side (output cables) and 500mm (20’’) of clearance in the remaining sides of the cabinet.

 

 

Input Power Cables 

AC input cables must be copper with appropriate power rating. 
 
EFAPOWER EV-QC45 can be placed in 3 alternative positions as showed in Figure 5. 
 

 

Figure 5 - EFAPOWER EV-QC45 alternative orientations  

Summary of Contents for EFAPOWER EV-QC45

Page 1: ...loser than 6 1m 20 feet of an outdoor motor fuel dispensing device EFAPOWER EV QC45 is in an IP54 IK10 NEMA 3R enclosure This Unit is intended to work below 50ᵒC 122ᵒF ambient temperature Clearance around the cabinet The air must circulate freely throughout the ventilation grids in order for the charger s cooling system to be effective The ventilation areas on the sides and back must not be blocke...

Page 2: ... temperatures heavy dust snow and or very low temperatures it s recommended to provide additional protection either inside a building or a shelter or providing a protection roof for the Unit See example in Figure 6 Figure 6 EFAPOWEREV QC45 with shelter 5 1 2 SITE VERIFICATION AND INSPECTION Check if the installation of the Quick Charger is not planned to be made in a commercial garage repair facil...

Page 3: ... outputs connections not available for USA market Requires a dedicated 160A circuit breaker 3P C curve Figure 7 EFAPOWEREV QC45Wiring Information NOTES In areas with frequent thunder storms Efacec recommends adding transient voltage surge suppression TVSS at the service panel for all circuits Unless required by local codes it is not necessary to install a residual current device RCD for the circui...

Page 4: ... 2 above the concrete and 89 5mm 3 52 into the concrete 4 four sealing screws Socket head button cap screws M12x25 metric with matching flat rubber washers supplied with the Quick Charging Station End terminals for input wiring Depending on the EFAPOWER EV QC45 configuration Only DC outputs 5 five end terminals up to 35mm2 3phases neutral protective ground or DC and AC outputs not available for US...

Page 5: ... WxDxH 1150x850x2150mm 45 3x33 5x84 6 inches 5 3 2 VISUAL INSPECTION Check if the exterior packaging has been damaged by mechanical impacts or any accidents during transportation If applicable check if the exterior panels of the EFAPOWER EV QC45 are in perfect condition Check if the interior of the Quick Charger Station is clean Check if the door of the Quick Charger Station is working properly Ch...

Page 6: ...4 ASSEMBLY PLACING INSTRUCTIONS 5 3 4 1 ANCHORING TO THE CONCRETE PAD The Quick Charging Station must be anchored on the surface compliant with the specifications mentioned in chapter 5 2 2 The power cabinet must be installed on a concrete pad using 4 four chemical anchors M8 5 16 10mm thread diameter length must comply with local codes but must have at least 120mm 5 In the following figure some d...

Page 7: ...instructions For the Power Cabinet it s advised to have a concrete block of at least 1000mm 34 9 square by 254mm 10 deep Check local codes to ensure compliance The bolts must extend at least 30 5mm 1 2 above the concrete and 89 5mm 3 52 into the concrete ALL SERVICING MUST BE PERFORMED ONLY BY QUALIFIED PERSONNEL DO NOT ATTEMPT TO SERVICE THE EFAPOWER EV QC45 QUICK CHARGING STATION YOURSELF DO NOT...

Reviews: