5. Commission the pump
To commission the pump:
1.
Make sure that the voltage selection is set to correct value required for the
application. Refer to
Figure: Voltage selection plate
on page 20.
2.
Make sure that the exhaust extraction system is not blocked (for example, that
valves in the exhaust extraction system are open).
3.
Make sure that all openings to atmospheric pressure in the foreline vacuum system
are closed.
4.
Set the external electrical supply to ON.
5.
Set the mains circuit breaker (
on page 8, (8)) to ON. Make sure
that the power indicator LED (
Figure: Interface control panel
on page 9, (14))
illuminates. If the LED does not illuminate, contact us.
6.
Press the start button (
Figure: Interface control panel
on page 9, (1)) until the run
indicator LED (
Figure: Interface control panel
on page 9, (13)) begins to flash.
7.
If the dry pumping system starts and continues to operate, continue at Step 8. If an
alarm condition is indicated:
A.
shut down the dry pumping system. Refer to
on page 29.
B.
contact us.
8.
After you commission the dry pumping system:
A.
to continue to operate the system, refer to
on page 29.
B.
to shut down the system, refer to
on page 29.
Page 21
A90301880_B - Commission the pump