ECR International GreenMountain GMGS075E Installation, Operation & Maintenance Manual Download Page 8

8

SYSTEM PIPING

Consider near boiler piping as part of the boiler for proper 

water level control and to produce dry steam. 
Correct near boiler piping is crucial to proper operation of 

boiler and heating system.
Follow these recommendations carefully.

1. 

Place boiler in selected location as near chimney as 

possible. 

2. 

Install safety valve. Figure 3 and Warning on Page 7.
• Install union, if used, close to safety valve outlet.
• Install elbows close to safety valve outlet and 

downstream of union (if used).

3. 

Boiler is equipped with two 2½" supply connections 

and two 2½" return connections, one each on both left 

and right sides of boiler. Plug unused connections with 

furnished 2½" plug (furnished).

4. 

When using both supply tappings to pipe system as 

shown in Figure 5, Page 10.

• Fit headers with header offsets, swing joints, or equip 

with expansion joints, so thermal expansion and 

contraction of header does not damage boiler. Do not 

weld headers.

• Place system takeoffs from header between equalizer 

and riser to header nearest equalizer. System takeoffs 

must never be between two risers. If steam main goes 

in two directions, place two takeoffs from header, one 

for each main.

5. 

System takeoffs from the header must never be 

bullheaded. If the steam main goes in two directions, 

there must be two takeoffs from

 the header, one for each 

main.

6. 

All boilers in gravity return systems

 must

 be equipped 

with a Hartford Loop as shown in Figure 5.

7. 

When piping the vertical risers from the boiler to the 

header, the bottom of the header must be a minimum 

of 24 inches above the water level line on the right side 

of the boiler.

8. 

Steam riser(s) and header shall be 2½” pipe size. 

9. 

Equalizer line shall be minimum 1½” pipe size.

10. 

The near boiler piping shall include a 2½” tee with a 

plug located on the supply line as shown for skimming 

(i.e. surface blowdown).

11. 

The near boiler piping shall include a 1-1/2 ball valve 

in the return piping as shown for bottom blowdown and 

draining.

12. 

For gravity return systems, the bottom of the lowest 

steam carrying pipe, be it a dry return, or the end of the 

steam main, must be at least 28” above the normal water 

level line on the right side of the boiler. This is known as 

“Dimension A.”

13. 

For pumped return systems, follow the condensate 

pump or boiler feed pump manufacturer’s instructions 

for proper installation and hookup.

14. 

In connecting the cold water supply to the water inlet 

valve, make sure that a clean water supply is available. 

When the water supply is from a well or pump, a sand 

strainer should be installed at the pump.

For Use With Cooling Units

Install boiler, when used in connection with refrigeration 

system, so chilled medium is piped in parallel with boiler 

with appropriate valves to prevent chilled medium from 

entering the boiler. See Figure 6.

Summary of Contents for GreenMountain GMGS075E

Page 1: ...Steam Gas Fired Boilers INSTALLATION OPERATION MAINTENANCE MANUAL Models GMGS075E GMGS225E GMGS112E GMGS262E GMGS150E GMGS299E GMGS187E Manufactured by ECR International Inc 2201 Dwyer Avenue Utica N...

Page 2: ...1 Dimensions Inches Intermittent Ignition w Vent Damper Flue Diameter A Width GMGS075E 5 11 GMGS112E 6 14 GMGS150E 6 17 GMGS187E 7 21 GMGS225E 7 24 GMGS262E 7 27 GMGS299E 7 30 Add 5 to height for Ven...

Page 3: ...GMGS299E 9 Natural Gas 299 245 82 0 184 767 MBH 1 000 Btuh Btuh British Thermal Unit Per Hour For altitudes above 2 000 ft reduce input rate 4 for each 1 000 ft above sea level Heating Capacity is ba...

Page 4: ...whatsoever Introduction Boiler is designed for use in closed heating systems where all steam is returned as condensate and make up water is minimal Boiler is not designed for or intended for use in o...

Page 5: ...any other gas appliance with improper methods or materials could result in death or serious injury due to fire or to asphyxiation from poisonous gases such as carbon monoxide which is odorless and in...

Page 6: ...conditions of use Boiler location should not interfere with proper circulation of air Introduce outside air if normal infiltration does not provide necessary air Fresh Air for Combustion on page 11 6...

Page 7: ...or place any obstruction in discharge line Terminate freely to atmosphere where any discharge will be clearly visible and at no risk of freezing Allow complete drainage of valve and discharge line Ins...

Page 8: ...from the header one for each main 6 All boilers in gravity return systems must be equipped with a Hartford Loop as shown in Figure 5 7 When piping the vertical risers from the boiler to the header th...

Page 9: ...9 Figure 4 Recommended Near Boiler Piping Using One Supply Tapping SYSTEM PIPING...

Page 10: ...LATION SYSTEM PIPING Figure 6 Chilled Water Piping VALVES A B OPEN FOR HEATING CLOSE FOR COOLING VALVES C D CLOSE FOR HEATING OPEN FOR COOLING Figure 5 Recommended Near Boiler Piping Using Two Supply...

Page 11: ...ter than 0 60 Room volume is greater than 21 cubic feet divided by ACH air changes per hour x Total Input Mbh C Refer to National Fuel Gas Code for opening requirements between connected indoor spaces...

Page 12: ...uld not be longer than 3 4 the chimney height HT Figure 7 page 13 Vent Pipe Fasten sections of vent pipe with 3 sheet metal screws at each joint to make piping rigid Support horizontal portions of ven...

Page 13: ...er gas burning appliance to their previous conditions of use 7 Any improper operation of the common venting system should be corrected so the installation conforms with the National Fuel Gas Code ANSI...

Page 14: ...on and for vent damper troubleshooting guide refer to manual packaged with vent damper Horizontal Installation To Boiler Vent Damper To Chimney NO NO YES YES Flow Install vent damper with actuator to...

Page 15: ...or dampen excessive vibrations and prevent strain on gas connection Gas valve will not support piping weight Use thread joint compound pipe dope suitable for natural and liquefied petroleum gas Insta...

Page 16: ...ut off two wires are black One wire is located on secondary of 24 volt transformer second wire is located on pressure limit control F Boilers with PS 802 probe type low water cut off one wire is green...

Page 17: ...ol knob slightly and turn clockwise to OFF Do not force For Your Safety Read Before Operating WARNING If you do not follow these instructions exactly a fire or explosion may result causing property da...

Page 18: ...wn on left side of boiler Determine water level when boiler is off and cold when all water in the system is inside the boiler and return piping below water line and everything above water line is air...

Page 19: ...inner cones in softer blue outer mantel with no yellow Remain still when observing main burner flames Check main burner orifices burner throat and flame ports for dust and lint obstruction if flame ap...

Page 20: ...ower on and turn thermostat to call for heat C Gas valve opens for approximately 10 seconds time delay on probe type LWCO gas valve will close and red indicator illuminates on LWCO D When water is res...

Page 21: ...ild up Run connection from boiler drain valve to safe discharge point outside Shut off gas burners open drain valve allow all of water in boiler to drain out Close drain valve Allow boiler to cool slo...

Page 22: ...bead of 400 F RTV silicone to four mounting surface flanges of flue collector Mount flue collector on heat exchanger Tighten nuts and bolts 6 Seal front edge and four corners of flue collector to hea...

Page 23: ...e joints Rollout switch blown Have your service technician check heat exchanger for blockage Chimney flue is blocked Spill switch contacts open requiring manual reset of spill switch Have your service...

Page 24: ...s appliance must be replaced it must be replaced with type 105 C Thermoplastic wire or its equivalent Figure 13 Wiring Diagrams For Boilers With PS 802 Probe Type Low Water Cut Off Shown PS802 PS802 C...

Page 25: ...ny of the original wire as supplied with this appliance must be replaced it must be replaced with type 105 C Thermoplastic wire or its equivalent Figure 17 Wiring Diagrams For Boilers With 67D 1 Float...

Page 26: ...l Model WF 2U 24 water feeder maybe used with either of the low water cutoffs listed Water feeder maintains safe minimum water level Keeps boiler running by compensating for minor evaporative steam le...

Page 27: ...27 REPAIR PARTS...

Page 28: ...28 REPAIR PARTS...

Page 29: ...29 REPAIR PARTS...

Page 30: ...30 REPAIR PARTS Safety Relief Valve 14 11 NPT X 4 Nipple PF 033 02...

Page 31: ...31 Date Service Performed Company Name Tech Initials Company Address Phone...

Page 32: ...Manufactured by ECR International Inc 2201 Dwyer Avenue Utica NY 13501 web site www ecrinternational com...

Reviews: