Ecofoot2Plus_Install_Guide_V1.6-FINAL
Page 7 of 12
January 5, 2018, ES10560
ecolibriumsolar.com
E
™
Installation Instructions
2
Place Lower Clamp (B) and Upper Clamp (C) into
E Base (A) as shown. Push Clevis Pin (D)
completely into E® Base(A) to secure Rocker.
Tip: Only install Clamps where modules will rest. Refer to diagram
below for correct placement and orientation of Clamps.
C
B
D
D
3
Place module onto E® Base (A). Using a 1/2"
deep socket, torque Nuts (F) to 14 ft-lbs. Space modules
1/2“apart using the alignment marks on the Clamps.
1
Chalk lines on roof denoting two outside edges of the
E® according to project drawing. Place
E® Bases (A) in position.
Tip: Ensure lines are square using 3-4-5 principle.
Tip: As you build the array, panels will space Bases. Roughly place
a few rows of Bases at a time so that they are within reach of final
location.
Tip: If installation requires 2 blocks or fewer on the north row,
north row Bases can be turned around 180 degrees and tucked
under the panel.
Tip: If installation requires butyl, then butyl will be preinstalled on
the bottom of the Base with protective tape. Ensure these butyl
components are placed where specified in project drawing.
Remove protective tape after step 6.
A
3