JINECO02 RevG 11/06/12
Commissioning & Handover
Upon completion of the installation, allow a
suitable period of time for any fire cement and
mortar to dry out.
A small fire may then be lit and checked to
ensure the smoke and fumes are taken from the
stove up the chimney and emitted safely to
atmosphere.
Do not run the stove at full output for at least
24 hours.
On completion of
the installation
and
commissioning, ensure that the operating
instructions and operating tools for the stove
are left with the customer.
Advise the customer on the correct use of the
appliance with the fuels likely to be used on the
stove and warn them to use only the
recommended fuels for the stove.
Advise the user on what to do should smoke or
fumes be emitted from the stove.
The user should be warned to use a fireguard to
BS 8423 in the presence of children and/or
infirm persons.