GP1/HP1/SP1 D
UCT
& P
LENEM
P
ROBES
- I
NTERNAL
M
OUNT
Q
UICK
I
NSTALLATION
G
UIDE
a measurable difference!
EBTRON
®
3
FINAL ASSEMBLY FOR STANDARD PROBES
12.
Ensure that provision has been made for an appropriate cable exit hole through the duct/plenum. The cable
exit hole must be of sufficient size to pass the probe connector (which is approximately 0.85 in [20.8 mm]) PLUS
any other cables planned for this exit hole. The edges of the cable exit hole must be prepared to ensure that no
damage occurs to cable or insulating jacket during or after installation.
13.
Loosen the Non-Cable End Adjustment Screws on both sides of the probe as shown in the detail of Figure 2
for Standard Probes to permit pivoting the probe and bracket.
14.
Carefully place the non-cable end bracket at the non cable end marked location on the inside of the duct
wall so that when the probe is installed, airflow will be in the direction of the arrows printed on the bracket and/or
probe. For ease of installation, the probe can pivot within the bracket after loosening the non-cable end Adjustment
Screws (completed in step 13).
NOTE:
If the airflow direction labels are not visible on the bracket and/or probe, orient the probe so
that the sensor SET SCREWS (two per sensor insert) face the DOWNSTREAM side of the
probe as shown in Figure 2. (There are no setscrews on the upstream side of the sensor
inserts).
15.
Fasten the Non-Cable End mounting bracket to the duct at two places with appropriate field supplied
fasteners, again making sure that printed airflow arrows on the bracket and/or probe are in the actual direction of
duct air flow.
16.
Carefully route the probe cable through the cable exit hole prepared in step 12, and pivot the cable end
probe bracket to the marked location on the duct wall.
17.
Fasten the cable end mounting bracket to the duct at two places with appropriate field supplied fasteners,
again making sure that printed airflow arrows on the bracket and/or probe are in the actual direction of duct air
flow.
18.
Slightly loosen the cable end probe Adjustment screws on both sides of the probe to permit probe movement
within the bracket.
19.
Carefully center the probe in the duct opening, and then tighten the probe Adjustment Screws on both sides
of the cable end bracket, and then on both sides of the non-cable end bracket as shown in Figure 2 detail. (There
are 4 Adjustment Screws total).
20.
Repeat steps 12 through 19 for all probes.
21.
Seal all cable exit holes with suitable sealant material.
22.
Connect all sensor probes to the transmitter supplied for the specific location. This completes probe
installation.
Complete the installation, wiring and set up of the associated transmitter as detailed in the separate Transmitter
Installation Guide and the Installation, Operation and Maintenance Technical Manual (each provided under
separate cover).