4. CONNECTION AND START-UP

4.1 Connecting the mechanical system

CAUTION
Cutting and crushing hazard when removing the device
from the packaging

Blades can be bent
→ Carefully remove the device from its packaging, only

touching the wall ring. Make sure to avoid any shock.

→ Wear safety shoes and cut-resistant safety gloves.

;

Check the device for transport damage. Damaged devices must no
longer be installed.

;

Install the undamaged device according to your application.

4.2 Connecting the electrical system

DANGER
Electric voltage on the device

Electric shock
→ Always install a protective earth first.
→ Check the protective earth.

DANGER
Incorrect insulation

Risk of fatal injury from electric shock
→ Use only cables that meet the specified installation

requirements for voltage, current, insulation material, load etc.

→ Route cables such that they cannot be touched by any

rotating parts.

CAUTION
Electrical voltage

The fan is a built-in component and features no electrically
isolating switch.
→ Only connect the fan to circuits that can be switched off with

an all-pole separating switch.

→ When working on the fan, you must switch off the

installation/machine in which the fan is installed and secure it
from being switched on again.

CAUTION
Electric shock

Electric voltage on the metal part
→ Use the device only with the cable guard and terminal box

provided for this purpose.

NOTE
Water penetration into leads or wires

Water enters at the cable end on the customers side and can
damage the device.
→ Make sure that the cable end is connected in a dry

environment.

Connect the device only to circuits that can be switched off
using an all-pole disconnecting switch.

4.2.1 Prerequisites

;

Check whether the data on the type plate agree with the connection
data and the data of the operating capacitor.

;

Before connecting the device, ensure that the supply voltage matches
the operating voltage of the device.

;

Only use cables designed for current according to the type plate.
For determining the cross-section, follow the basic principles in
accordance with EN 61800-5-1. The protective earth must have a
cross-section equal to or greater than the outer conductor cross-
section.
We recommend the use of 105°C cables. Ensure that the minimum
cable cross-section is at least
AWG26/0.13 mm².

4.2.2 Voltage control

With open loop speed control using transformers or electronic
voltage regulators (e.g. phase angle control), excessive current
may occur.
In addition, noises can occur with phase angle control
depending on the mounting situation.

4.2.3 Frequency inverter

Fit sinusoidal filters that work on all poles (live-live and live-
earth) between the frequency inverter and the motor for
operation with frequency inverters.
Depending on how the device is installed, noises may occur.

4.3 Connection in terminal box

4.3.1 Preparing connection lines for the connection

Strip the cable just enough so that the screwed cable gland is tight and
the terminals are relieved of strain. Tightening torque, see chapter 3.1
Product drawing.

4.3.2 Connecting cables with terminals

;

Remove the cap from the screwed cable gland.

Remove the cap only in those places where cables are inserted.

;

Insert the line(s) (not included in the standard scope of delivery) into
the terminal box.

;

First connect the "PE" (protective earth) connection.

;

Connect the lines to the corresponding terminals.

Use a screwdriver to do so.
During the connection work, ensure that no cables splice off.
The terminal strip is equipped with a penetration prevention device.

;

Insert the strands until they meet resistance.

;

Seal the terminal box.

Item no. 10705-5-9970 · Revision 69285 · Release 2009-11-30 · Page 6 / 10

ebm-papst Mulfingen GmbH & Co. KG · Bachmühle 2 · D-74673 Mulfingen · Phone +49 (0) 7938 81-0 · Fax +49 (0) 7938 81-110 · [email protected] · www.ebmpapst.com

Summary of Contents for W2E250-CE65-26

Page 1: ...y trained and authorised specialist personnel are permitted to transport unpack assemble operate or maintain the device or to use it in any other manner 1 3 Basic safety rules 1 1 3 Basic safety rules...

Page 2: ...the device You could be injured Do not wear any loose clothing or jewellery while working on rotating parts Protect long hair by wearing a cap 1 7 Emission WARNING Depending on the installation and o...

Page 3: ...particularly prohibited and may cause hazards Operating the device with an imbalance e g caused by dirt deposits or icing Opening the terminal box during operation Moving air that contains abrasive p...

Page 4: ...m 1 Direction of air flow A 2 Tightening torque 0 5 Nm 3 Illustration without terminal box cover 4 Cable diameter max 7 5 mm tightening torque 2 Nm Item no 10705 5 9970 Revision 69285 Release 2009 11...

Page 5: ...position Shaft horizontal or rotor on bottom rotor on top on request Condensate discharge holes Rotor side Operation mode S1 Motor bearing Ball bearing Touch current acc IEC 60990 measuring network Fi...

Page 6: ...data and the data of the operating capacitor Before connecting the device ensure that the supply voltage matches the operating voltage of the device Only use cables designed for current according to...

Page 7: ...Ill 2 Fan installed lying flat cable routed as a water trap Fans installed in upright position When routing the cable ensure that the screwed cable glands are arranged at the bottom The cables must al...

Page 8: ...uctions 4 4 Connection screen L U1 blue Z brown N U2 black PE green yellow Item no 10705 5 9970 Revision 69285 Release 2009 11 30 Page 8 10 ebm papst Mulfingen GmbH Co KG Bachm hle 2 D 74673 Mulfingen...

Page 9: ...CAUSES AND REMEDIES The motor is sealed by ebm papst Changes or repairs may be carried out by ebm papst only The terminal box does not have to be opened for maintenance Do not perform any repairs on...

Page 10: ...evice Check the device for damage to blades and housing Visual inspection At least every 6 months Replacement of the device Mounting the connection lines Visual inspection At least every 6 months Fast...