4.5 Checking connections

;

Ensure isolation from supply (all phases).

;

Make sure a restart is impossible

;

Check the cables for proper fit.

4.6 Switching on the device

The device may only be switched on if it has been installed properly and
in accordance with its intended use, including the required safety
mechanisms and professional electrical hookup. This also applies for
devices which have already been equipped with plugs and terminals or
similar connectors by the customer.

;

Before switching on, check the device for visible external damage
and make sure the protective devices are functional.

;

Check the fan's air flow paths for foreign matter and remove any
foreign matter found.

;

Apply the nominal supply voltage.

4.7 Switching off the device

;

Disconnect the device from the power supply at the supply line's
main switch.

5. MAINTENANCE, MALFUNCTIONS, POSSIBLE
CAUSES AND REMEDIES

Do not perform any repairs on your device. Send the device to ebm-
papst for repair or replacement.

WARNING
Live terminals and connections even with device
switched off

Electric shock
→ Wait five minutes after disconnecting the voltage at all poles

before opening the device.

CAUTION
Electric charge on capacitor after device is switched off

Electric shock, risk of injury
→ Discharge the capacitors before working on the device.

CAUTION
The motor restarts automatically when operating voltage
is applied, e.g. after a power failure.

Risk of injury
→ Keep out of the motor's danger zone.
→ When working on the motor, switch off the line voltage

and ensure that it cannot be switched back on.

→ Wait until the motor comes to a stop.

NOTE

If the device is not operated for a lengthy period in installed
condition in a dry environment, it is to be started up and
operated at full speed for one hour at least every four months. If
the device is not operated for a lengthy period in installed
condition in a damp environment (e.g. outdoors), it is to be
started up and operated at full speed for at least two hours once
a month to move the bearings and allow any condensate that
may have ingressed to evaporate.

Malfunction/fault

Possible cause

Possible remedy

Rotor not running
smoothly

Imbalance in rotating
parts

Clean the device;
replace it if imbalance
persists after cleaning

Motor not turning

Mechanical blockage

Switch off, isolate
from supply and
remove mechanical
blockage.

Line voltage faulty

Check line voltage,
restore power supply.

Faulty connection

Isolate from supply,
correct connection;
see connection
diagram.

Thermal overload
protector activated

Allow motor to cool
off, locate and rectify
cause of error,
release restart lockout
if necessary

Impermissible point of
operation

Check point of
operation

Motor
overtemperature

Ambient temperature
too high

Reduce ambient
temperature if possible

Deficient cooling

Improve cooling

In the event of further malfunctions, contact ebm-papst.

5.1 Cleaning

NOTE
Damage to the device during cleaning

Malfunction possible
→ Do not clean the device using a water jet or high-pressure

cleaner.

→ Do not use any acid, alkali or solvent-basedcleaning

agents.

→ Do not use any pointed or sharp-edged objects for cleaning

5.2 Safety inspection

What to check

How to check

How often

What action?

Device for
damage

Visual inspection At least every

6 months

Replace device

Fastening the
cables

Visual inspection At least every

6 months

Fasten

Insulation of
cables for
damage

Visual inspection At least every

6 months

Replace cables

Abnormal
bearing noise

acoustic

At least every
6 months

Replace device

5.3 Disposal

For ebm-papst, environmental protection and resource preservation are
top priority corporate goals.
ebm-papst operates an environmental management system which is
certified in accordance with ISO 14001 and rigorously implemented
around the world on the basis of German standards.
Right from the development stage, ecological design, technical safety
and health protection are fixed criteria.

Item no. 12519-5-9970 · ENU · Change 202174 · Approved 2018-12-28 · Page 9 / 10

ebm-papst Mulfingen GmbH & Co. KG · Bachmühle 2 · D-74673 Mulfingen · Phone +49 (0) 7938 81-0 · Fax +49 (0) 7938 81-110 · [email protected] · www.ebmpapst.com

Summary of Contents for M4E068-EC03-49

Page 1: ...stalled operated maintained and otherwise used by suitably qualified trained and authorized technical staff Only authorized specialists are permitted to install the device to carry out a test run and...

Page 2: ...elry and the like can become entangled and be pulled into the device Injuries can result Do not wear any loose fitting or dangling clothing or jewelry while working on rotating parts Protect long hair...

Page 3: ...ant operation operation with severe vibration oscillation This also includes vibration transmitted to the motor from the customer installation Operation in medical equipment with a life sustaining or...

Page 4: ...duct drawing All dimensions in mm 1 Cable PFA AWG20 6x crimped splices 2 Max clearance for screw 5 mm Item no 12519 5 9970 ENU Change 202174 Approved 2018 12 28 Page 4 10 ebm papst Mulfingen GmbH Co K...

Page 5: ...f the device are designed for a maximum of one million load cycles If you have special questions consult ebm papst for support Use the device in accordance with its degree of protection Information on...

Page 6: ...or the current level indicated on the nameplate For determining the cross section note the sizing criteria according to EN 61800 5 1 The protective earth must have a cross section equal to or greater...

Page 7: ...tched back on NOTE Lack of motor protection Without motor protection the motor can overheat and suffer damage Connect the thermal overload protector installed in the winding The motors are equipped wi...

Page 8: ...m 1 Clockwise operation 2 Counterclockwise operation U1 black U2 gray Z1 blue Z2 brown TOP 2x white Item no 12519 5 9970 ENU Change 202174 Approved 2018 12 28 Page 8 10 ebm papst Mulfingen GmbH Co KG...

Page 9: ...arted up and operated at full speed for at least two hours once a month to move the bearings and allow any condensate that may have ingressed to evaporate Malfunction fault Possible cause Possible rem...

Page 10: ...mostly made of steel copper aluminum and plastic Metallic materials are generally considered to be fully recyclable Separate the components for recycling into the following categories Steel and iron...

Reviews: