4.2.3 Idle current

Because of the EMC filter integrated for compliance with EMC
limits (interference emission and interference immunity), idle
currents in the mains cable can be measured even when the
motor is at a standstill and the mains voltage is switched on.

The values lie in a range of typical < 350 mA.

The effective power in this operating state (readiness for operation) is
simultaneously at typical < 6 W.

4.2.4 Residual current operated device

Only universal (type B or B+) RCD protective devices are
permitted. Like frequency inverters, RCD protective devices
cannot provide personal safety while operating the device.
When switching on the power supply of the device, pulsed
charge currents from the capacitors in the integrated EMC filter
can lead to the RCD protective devices triggering without
delay. We recommend residual current devices with a trigger
threshold of 300 mA and delayed triggering (super-resistant,
characteristic K).

4.2.5 Leakage current

For asymmetrical power systems or if a phase fails, the
leakage current can increase to a multiple of the nominal value.

4.2.6 Locked-rotor protection

Due to the locked-rotor protection, the start-up current (LRA) is
equal to or less than the nominal current (FLA).

4.3 Connection in terminal box

4.3.1 Preparing connection lines for the connection

Strip the cable just enough so that the screwed cable gland is tight and
the terminals are relieved of strain. Tightening torque, see chapter 3.1
Product drawing.

Fig. 1: Recommended stripping lengths in mm (inside the terminal box)
Legend: CL = control lines

4.3.2 Connecting cables with terminals

WARNING
Terminals and connections have voltage even with a
unit that is shut off

Electric shock
→ Wait five minutes after disconnecting the voltage at all poles

before opening the device.

;

Remove the cap from the screwed cable gland.

Remove the cap only in those places where cables are inserted.

;

Insert the line(s) (not included in the standard scope of delivery) into
the terminal box.

;

First connect the "PE" (protective earth) connection.

;

Connect the lines to the corresponding terminals.

Use a screwdriver to do so.
During the connection work, ensure that no cables splice off.

Fig. 2: Connecting the wires to terminals

;

Seal the terminal box.

4.3.3 Cable routing

No water may penetrate along the cable in the direction of the cable gland.
When routing the cable, ensure that the screwed cable glands are
arranged at the bottom. The cables must always be routed downwards.

Item no. 51234-5-9970 · ENG · Revision 82539 · Release 2014-05-08 · Page 7 / 12

ebm-papst Mulfingen GmbH & Co. KG · Bachmühle 2 · D-74673 Mulfingen · Phone +49 (0) 7938 81-0 · Fax +49 (0) 7938 81-110 · [email protected] · www.ebmpapst.com

Summary of Contents for K3G800-AQ03-01

Page 1: ...are permitted to install the device to carry out a test run and to perform work on the electrical installation 1 3 Basic safety rules 1 1 3 Basic safety rules Any safety hazards stemming from the devi...

Page 2: ...appropriate safety measures WARNING Rotating device Long hair loose items of clothing and jewellery could become entangled and pulled into the device You could be injured Do not wear any loose clothi...

Page 3: ...nsport and storage conditions and chapter 3 2 Nominal data Operating the device with all protective features in place Minding the operating instructions Improper use Using the device in the following...

Page 4: ...545 2 Screw on position for vibration absorbing elements 3 Cable diameter min 4 mm max 10 mm tightening torque 4 0 6 Nm 4 Cable diameter min 9 mm max 16 mm tightening torque 6 0 9 Nm 5 Tightening torq...

Page 5: ...side Operation mode S1 Motor bearing Ball bearing Technical features Output 10 VDC max 10 mA Output 20 VDC max 50 mA Output for slave 0 10 V Input for sensor 0 10 V or 4 20 mA External 24 V input prog...

Page 6: ...ance to the power supply line when routing the control lines of the device Ensure a sufficiently large clearance Recommendation clearance 10 cm separate cable routing NOTE Water penetration into leads...

Page 7: ...ss than the nominal current FLA 4 3 Connection in terminal box 4 3 1 Preparing connection lines for the connection Strip the cable just enough so that the screwed cable gland is tight and the terminal...

Page 8: ...g Control mode parameter set 2 PWM controlling Fan device adress 01 Max PWM 100 Min PWM 8 Save set value to EEPROM Yes Set value control Analogue linear Control function parameter set 1 Positive heati...

Page 9: ...n pin or applied voltage 5 50 VDC disabling bridge to GND or applied voltage 1 VDC reset function triggers software reset after a level change to 1 VDC SELV KL 3 8 Din2 Digital input 2 parameter set s...

Page 10: ...fan for foreign objects and remove any that are found Apply the nominal voltage to the voltage supply Start the device by changing the input signal 4 8 Switching off the device Switching off the devi...

Page 11: ...Switch off de energise and remove mechanical blockage Mains supply voltage faulty Check mains supply voltage restore power supply Important The error message resets automatically The device starts up...

Page 12: ...nst accidental contact for damage and to ensure that it is intact Visual inspection At least every 6 months Repair or replacement of the device Check the device for damage to blades and housing Visual...

Reviews: