15
5. Fastening of heating cable must be done with c/c 20 cm.
2 cm
Tape
Adhesive/Cable clip
6. Perform other insulation and resistance measurements and
fill in the test report or Garantera on your smartphone. Docu-
ment the location of the cable with a photo.
8. If possible, after applying screed, alternatively after floor-
ing has been laid, perform a third insulation and resistance
measurement of the heating cable. Fill in the test report or use
Garantera on your smartphone.
For tiles, wait 4 weeks after installation before turning on the heat.
M
Ω
/
Ω
Ebeco Cable Board is an insulation board especially
designed for Cable Kit/Cableflex under tiled and
natural stone floors. It has grooves for laying the heating
cable and consequently provides quick and uniform
positioning of the heating cable without the need of
manually measuring centre-to-centre distances. The
insulation board's properties make the underfloor
heating system extremely responsive to adjustments.
Compared to the reference installation (60s-70s house
with an uninsulated floor construction of 15 cm thick
concrete slab on the ground), Cable Board provides an
energy saving of up to 45%. On concrete surfaces, it can
be used both in wet rooms and dry areas. On wooden
surfaces, it may only be used in dry areas and then
replaces the plasterboard in the floor construction. In
wet rooms with wooden subfloors, Ebeco Thermo Board is
recommended.
Energy-saving tips!
7. Cover the floor with a suitable floor filler. Keep in mind that
the cable must be under the sealing layer in wet rooms.
EN