1. Acceptance Check
Check the following items on receipt of the pump package.
(1) Check that the nameplate affixed to the outer cover of the pump to confirm that the pump supplied
agrees with your order. Check the accessories against the packing list and the previously
submitted drawings and documents to confirm that the all ordered accessories have been supplied.
(2) Check that no damage for the pump has occurred in transit.
(3) Store the pump in a dry and clean place if it is not installed at once after delivery.
Temperature :
5
℃
to 40°C
Humidity
:
80% or less
Note
Notify EBARA without delay when damage is discovered or when components are missing.
Do not use when a leak is present as this will result in accident.
Note
Placed the pump in an upright position. Do not stack as packing. When the pump is
overturned, this will result in accident.
Summary of Contents for EV-PA 250
Page 11: ...P 11 PM10U EBARA CORPORATION...
Page 12: ...P 12 PM10U EBARA CORPORATION...
Page 20: ...P 20 PM10U EBARA CORPORATION 2 3 2 Outline Drawing EV PA250...
Page 21: ...P 21 PM10U EBARA CORPORATION EV PA500...
Page 33: ...P 33 PM10U EBARA CORPORATION...
Page 34: ...P 34 PM10U EBARA CORPORATION LCD BL LCD BL AUTO...
Page 51: ......