The wiring of the RS-485 port terminals of the hybrid inverter 

and the power meters terminals is illustrated in Figure 9:

• 

Connect the RS-485 terminals of the power meter to 

the RS-485 terminal block using a 1 mm

2

 cable, which is 

included in the accessory box kit mentioned in the xStorage 

Home installation manual;

• 

The connection to the RS-485 connection port of the hybrid 

inverter should be realized via the RS-485 terminal block.

For the hybrid inverter to establish communications with the 

power meters through its RS-485 port, the address of the 

RS-485 port inside the power meter must be changed from its 

default setting of “0075” to:

• 

0001

 for power meter 1;

• 

0002

 for power meter 2.

The process for setting the communications parameters 

is the same for both power meters, with the exception of 

their assigned addresses. Enter the programming mode as 

described:

1.  Power up the meter and irrespective of the 

measurement message displayed (see display 

example) keep pressing the navigation keys      and   

for more than three seconds until the word “Code” 

appears on the LCD display.

The design of the RS-486 connector terminals is illustrated in 

Figure 10.

Figure 9: Wiring the hybrid inverter and the power meters 

via the RS-485 port

Figure 11: Power meter icons in the xStorage Home 

installation diagrams

Figure 10: RS-485 connector terminals

Once the electrical installation has been carried out, the 

power meter must be properly configured in order to ensure 

the activation of the correct measuring mode and the correct 

communications flow to the xStorage Home system, i.e. 

to its hybrid inverter unit. The following illustrations explain 

the communication configuration for the power meters, i.e. 

for power meter 1 and power meter 2, whose purpose is 

explained in the xStorage Home installation manual.

Summary of Contents for xStorage Home Series

Page 1: ...xStorage Home Power Meters Manual For 4 2 kWh 6 kWh and 10 kWh systems capacity This document is intended for Eaton certified installers xStorage Home...

Page 2: ...know 3 3 SFERE DDS1946 DS Technical specifications installation and wiring 4 4 SFERE DTS1946 DS Technical specifications installation and wiring 8 5 Eastron SDM120CT Technical specifications installat...

Page 3: ...ustomer service we provide all specifications contained in this document are subject to change with due notice All drawings descriptions or illustrations contained in this document serve to provide a...

Page 4: ...nterface 2 the energy pulse indication light 3 the menu navigation keys 4 the model number Figure 3 SFERE DDS1946 DS product dimensions Figure 4 DIN rail mounting style overview Figure 5 Terminal wiri...

Page 5: ...UI to record the event history and to display the current energy consumption of both the critical and non critical loads as well as to track the PV generated energy as applicable The general wiring of...

Page 6: ...r both power meters with the exception of their assigned addresses Enter the programming mode as described 1 Power up the meter and irrespective of the measurement message displayed see display exampl...

Page 7: ...interface Please follow the instructions provided in the complementary xStorage Home user interface onboarding process manual 6 Again press to enter the third level menu This will display the default...

Page 8: ...re required The meter connection terminals must be directly connected to the L1 L2 L3 lines and N neutral wires Figure 16 L1 L2 L3 and N left side in the diagram is the side connected to the xStorage...

Page 9: ...id inverter The wiring of the RS 485 port terminals of the hybrid inverter and the power meters terminals is illustrated in Figure 19 Connect the RS 485 terminals of the power meter to the RS 485 term...

Page 10: ...ensure the activation of the correct measuring mode and the correct communications flow to the xStorage Home system i e to its hybrid inverter unit The following illustrations explain the communicatio...

Page 11: ...ied data and return to second level menu or b and at the same time to cancel the data modification and return to the second level menu 9 Press and to return to the first level menu i e the communicati...

Page 12: ...mpact electrical distribution box Figure 24 Figure 24 DIN Rail mount for Eastron meter During the installation of the power meter no additional protective devices are required The meter connection ter...

Page 13: ...appropriate meter is selected from the user interface The procedure starts with EM2 and then needs to be repeated for EM1 Please refer to the xStorage Home user interface onboarding process manual to...

Page 14: ...he power meter no additional protective devices are required The meter connection terminals must be directly connected to the L1 L2 L3 lines and N neutral wires The split core CT is installed on the L...

Page 15: ...r the correct password default 1000 before processing From the set up menu use the M and P buttons to select Address ID Press the Enter button to enter the selection routine The current setting will b...

Page 16: ...e la Longeraie 7 1110 Morges Switzerland Eaton com xstorage 2019 Eaton All Rights Reserved Publication No MN700001EN CSSC 1503 March 2019 Eaton is a registered trademark All other trademarks are prope...

Reviews: