![Eaton Power Xpert 9395C Installation And Operation Manual Download Page 99](http://html1.mh-extra.com/html/eaton/power-xpert-9395c/power-xpert-9395c_installation-and-operation-manual_4265554099.webp)
82
Eaton Power Xpert 9395C UPS Installation and Operation Manual 164000821—Rev 06
7.
Install wiring between the UPS and SCM II. See
and
for the Powerware Hot Sync CAN
Bridge Card terminal location and wiring information, and
,
, and
for the SCM II
terminal location and wiring information.
NOTE
120 Vac for the SCM II should be supplied from the critical bus by facility planners or the
customer.
8.
Install 120 Vac power wiring from the critical bus to the SCM II. See
, Figure 5-6
, and
for the terminal location and wiring information.
Figure 48. Supervisory Contact Module II Terminal Location.
Ground
Terminal
Terminal TB1 Signal
Connections from the UPS
Terminal TB3
120 Vac Power
Terminal TB2 Customer
Supervisory Contact Interface
NOTE
Setup of the Powerware Hot Sync CAN Bridge Card must be performed by an
authorized Eaton Customer Service Engineer. Contact an Eaton service representative
to schedule a date.
9.
Install wiring between the SCM II terminal block TB2 and the monitoring equipment. See
for
terminal block location and
for terminal assignments.
10. Close the front door and secure the latch.
11. Restart the UPS. See
for startup instructions.
Summary of Contents for Power Xpert 9395C
Page 8: ......
Page 175: ...16400082106 164000821 06...