52
Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201725—Rev 15
NOTE
For the following steps, verify that the forklift or pallet jack is rated to handle the weight
of the cabinet (see
) for cabinet weight).
1.
If not already accomplished, use a forklift or pallet jack to move the ISBM and UPM sections to the
installation area, or as close as possible, before unloading from the pallets. If possible, move each section
using the pallet. Insert the forklift or pallet jack forks from the right side of the pallet (facing the cabinet),
between the supports on the bottom of the pallet (see
,
and
for the ISBM and
UPM section center of gravity measurements). If the sections must be moved using the cabinet front or
rear fork lift slots, see the caution statements at the beginning of this procedure.
2.
Remove the three bolts securing the left side shipping bracket to the cabinet and three bolts securing the
bracket to the pallet (see
, or
). Remove the left side shipping bracket. If
installing the cabinet permanently, retain the shipping bracket and securing hardware for later use.
3.
Remove the three bolts securing the right side shipping bracket to the cabinet and three bolts securing the
bracket to the pallet (see
, or
). Remove the right side shipping bracket.
Figure 22. Removing the Left Side Shipping Bracket
Shipping Bracket
Bolts
Shipping Bracket
Bolts
Pallet
Left Side Shipping
Bracket
Front Door
Summary of Contents for Power Xpert 9395
Page 8: ......