Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201725—Rev 15
57
Figure 27. Removing the Two UPM Section Right Side Shipping Bracket
Shipping Bracket
Bolts
Shipping Bracket
Bolts
Pallet
Right Side Shipping
Bracket
44..33
M
Meecchhaanniiccaallllyy JJooiinniinngg tthhee S
Seeccttiioonnss
NOTE 1
The following procedure permits the UPS sections to be installed in a location where
there is limited space to slide the sections together from the sides.
NOTE 2
For the following steps, verify that the forklift or pallet jack is rated to handle the weight
of the section (see
for cabinet weight).
1.
Unfasten the front door latch and swing the door open (see
).
2.
Remove one top screw and two bottom screws securing the UPM section wireway panel (see
Lift the panel straight up to remove it from the panel hanger brackets at the top of the cabinet.
3.
Remove the screws securing the top and bottom internal safety shield panels and remove the panels.
Retain the hardware for later use.
4.
Remove the screws securing the corner channel and remove the channel (see
). Retain the
hardware for later use.