Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201716—Rev 13
67
7.
Remove the screws securing the internal safety shield panel and remove the panel. Retain the hardware
for later use.
8.
To gain access to terminal blocks TB1 and TB2 and the interface entry conduit landing plates, loosen the
screws securing the small top internal safety shield panel and remove the panel. This panel is to the right
of the X-Slot communication bays (see
).
9.
Remove the UPS cabinet interface entry conduit landing plates to drill or punch holes (see
).
10. Reinstall the interface entry plates and install conduit.
11. To locate the appropriate terminals and review the wiring and termination requirements, see
UPS System Power Wiring Preparation
, and
through
.
12. Route and connect the wiring as shown in
and
13. If the normally-closed REPO TB1 connection in the UPS is not used, connect a jumper wire between pins 1
and 2 on TB1.
14. If you are installing multiple REPO switches, wire additional switches in parallel with the first REPO.
Table 22. REPO Wire Terminations
From REPO Station(s)
Switch Contact Block
(Either Block)
To Customer Interface
Terminal Board TB1 in UPS
Cabinet
Wire Size
Tightening Torque
3 NO
TB1 3
Twisted Wires (2)
14 22 AWG (0.75
4.0 mm2)
7 lb in (0.8 Nm)
4 NO
TB1 4
Figure 31. Normally-Open REPO Switch Wiring
3 (NO)
UPS TB1
REPO
Switch
(NO)
Twisted
Wires
1 (NC)
NOTE
REPO switch rating is 24 Vdc, 1A minimum.
NOTE
T
he REPO switch must be a latching-type switch not tied to any other circuits.
NOTE
REPO normally-open and normally-closed return terminals are separated on the terminal board but are electrically in common.
2 (Return)
4 (Return)
3
4