Conduit sizes were chosen from NEC Table 4, Electrical Metallic Tubing (EMT). See Table 3-14 for conduit
requirements.
Per NEC article 300, 3(B)(1), all three-phase conductors must be run in the same conduit. The absence or
presence of neutral in the source and load wiring depends on whether the installation is a 4 wire or 3 wire type.
When the neutral is present, it must be run in the same conduit as the ground conductor and the phase
conductors.
Conduit is sized to accommodate one neutral conductor the same size as the phase conductor and one ground
conductor sized in accordance with NEC Table 250.122. For 3 wire configurations when neutral is not required,
the conduit sizes suggested below may be oversized.
Conduit sizes listed are for copper wiring only.
Table 3-11. Supplied Terminal Hardware Kit
Part
Size
Quantity
Terminals Used On
Eaton Part Number
Bolt, Grade 5
M10 x 30 mm
23
Ground and Neutral
180190078-088
Bolt, Grade 5
M12 x 45 mm
52
Rectifier Input, Bypass Input,
Battery Input, and Output
180190078-113
Flat Washer
M10
23
Ground and Neutral
180500036-100
Flat Washer
M12
104
Rectifier Input, Bypass Input,
Battery Input, and Output
180500036-120
Conical Washer
M10
23
Ground and Neutral
180500037-100
Conical Washer
M12
52
Rectifier Input, Bypass Input,
Battery Input, and Output
180500037-120
Nut
M12
52
Rectifier Input, Bypass Input,
Battery Input, and Output
180200001-07
Table 3-12. Recommended Installation Parts and Tools (Not Supplied by Eaton)
Part
Size
Quantity
Manufacturer
Part Number
Notes
Long Barrel 2-Hole Lug
2/0 AWG
As required
Thomas & Betts
54862BE
3/0 AWG
Thomas & Betts
54864BE
4/0 AWG
Thomas & Betts
54866BE
250 MCM
Thomas & Betts
54868BE
300 MCM
Thomas & Betts
54870BE
350 MCM
Thomas & Betts
54872BE
400 MCM
Thomas & Betts
54874BE
500 MCM
Thomas & Betts
54876BE
Manual Hydraulic Crimp Tool
14 Ton
1
Thomas & Betts
TBM14M
Die Set
N/A
1
Thomas & Betts
15506
Table 3-13. Separate Rectifier Input UPM Power Cable Terminations for the Power Xpert 9395-550/275
Terminal Function
Terminal
Function
Size of Pressure
Termination
Tightening Torque
Nm (lb ft)
Type Screw
AC Input to each UPM Rectifier
E1
Phase A
2 - #6-250 kcmil
42.4 (375)
5/16” Hex
E2
Phase B
2 - #6-250 kcmil
42.4 (375)
5/16” Hex
E3
Phase C
2 - #6-250 kcmil
42.4 (375)
5/16” Hex
Summary of Contents for Power Xpert 9395 550/275
Page 1: ...Power Xpert 9395 UPS 550 275 UPS 225 550 kVA Installation and Operation Manual...
Page 2: ......
Page 3: ...Power Xpert 9395 UPS 550 275 UPS 225 550 kVA Installation and Operation Manual...
Page 27: ...Section 1 Installation...
Page 28: ......
Page 207: ......
Page 208: ...164201716 8 164201716 8...