4
IL012287EN
Installation of PRLSEB type barrier kits
eaton
www.eaton.com
St
Part B
ep 2.
Installing the boots
Perform the following steps for each rubber boot, starting with the
center pole of the breaker.
A. Ensure the cables are maintained straight as far as possible from
the breaker. Install a cable tie around the conductors if multiple
conductors are to be inside the boot.
Figure 2. Installation of the PD2, PD3, PD4 & PD5 boots.
B. Install the large wire tie onto the end/top of the rubber boot
without fastening it. Note that the opening for the wire tie on
the rear of the boot will not be visible once the boot is installed.
C. Slide the rubber boot sub-assembly under and over the conduc-
tors. The opening should face the front of the panel.
D. Slide the boot towards the housing and align the bottom of the
boot with the housing.
E. Install the boot frame into the housing by pressing into place.
Ensure the boot is secured onto the four tabs in the housing.
PD3 Frame
PD4 Frame
PD5 Frame
PD2 Frame
Part A
Part A
Part B (x3)
Part B (x3)
Part B (x3)
Part B
Part A
Part A