INM 937x-FB2-Px-SS Rev 1

17

  a) Loosen the two screws securing the pluggable, spur-wiring connector to the  
    carrier and unplug it.

  b) Plug the Spur Surge module into the vacant socket on the carrier and tighten  
    the two fixing screws and its grounding screw, all to a recommended torque  
    of 0.4 Nm.

  c)  Loosen the spur cable gland.

  d) Withdraw approximately 20 mm of the cable length from the enclosure.

  e) Plug the spur connecting plug into its mating socket on the Spur Surge module  
    and tighten the fixing screws to a recommended torque of 0.4 Nm.

Make any final adjustments to the cable, to avoid any tension then tighten the spur 
cable gland to clamp the cable to retain the IP rating of the enclosure.

5 .5  Trunk connections

WARNING !

No part of the Trunk Terminal Assembly may be worked while the 

enclosure is powered, unless the environment is known to be  

non-hazardous.

Before any work starts on the Trunk Terminal Assembly the trunk power to the 
enclosure must be isolated, or a gas clearance certificate obtained.

Once the conditions are known to be safe, the protective plastic cover of the Trunk 
Terminal area may be removed.

Refer to Section 4.2.1 for additional information about trunk wiring connections.

When any changes or checks have been carried out, ensure there are no loose 
implements left inside the Trunk Terminal area before replacing its protective cover.

5 .6  Regular Maintenance checks

Check the general condition of the installation occasionally to ensure that no 
deterioration has occurred. At least every two years (and more frequently for harsh, 
dusty or dirty environments) check:

 

•  the condition of all wire connections/terminations/screens.

 

•  that all of the fixing and cover screws and blanking plugs are secure and the  

 

  breather is clear.

 

•  that there are no signs of damage or corrosion.

 

•  that the level of accumulated dust on the enclosure does not exceed 5mm.

WARNING !

If the outer enclosure of the apparatus needs to be cleaned, this should 

be done with a non-electrostatic generating cloth lightly moistened by a 

dilute mixture of detergent in water.

In addition, take advantage of plant maintenance shutdown periods or 

whenever the 

area is known to be non-hazardous,

 to check wiring quality by confirming that the 

dc voltage on the fieldbus trunk, when measured at the enclosure, is >16V. This can be 
performed using a multimeter or an FBT-6 fieldbus tester.

Summary of Contents for MTL CROUSE-HINDS Series

Page 1: ...937x FB2 Px SS Fieldbus Barrier System 6 spur 12 spur Stainless Steel enclosures November 2016 INM 937x FB2 Px SS Rev 1 Instruction manual MTL fieldbus networks...

Page 2: ...CLARATION OF CONFORMITY A printed version of the Declaration of Conformity has been provided separately within the original shipment of goods However you can find a copy of the latest version at http...

Page 3: ...runk Terminator F93 XE 11 4 5 Trunk Surge module 9376 SP 12 4 6 Spur connections 12 4 6 1 Connecting the spur cables 12 4 6 2 Fitting FS32 Spur Surge modules 12 4 7 Blanking plugs 13 4 8 Final checks...

Page 4: ...anking plugs or IP66 Ex eb tb Equipment certified cable glands All blanking plugs and glands must have a minimum temperature range 40 C to 75 C 2 IP66 Ex eb tb breather IECEx ATEX equipment certified...

Page 5: ...surge protection devices The enclosure material used for the wiring hubs is stainless steel SS and they are capable of being installed in a Zone 1 or Zone 2 hazardous area The following enclosure type...

Page 6: ...d socket above theTrunkTerminal area to protect the fieldbus barrier against damaging voltage and current surges on the incoming trunk wiring The enclosures may be installed in a Zone 1 or Zone 2 haza...

Page 7: ...the certification 3 2 Permitted enclosure combinations The maximum number of intrinsically safe spurs that can be supported per trunk segment using 937x FB2 range of Fieldbus Barrier enclosures is 18...

Page 8: ...73 FB2 Fieldbus Barrier System 12 Spur SS Enclosure BREATHER 138 5 SPUR 12 SPUR 11 SPUR 10 SPUR 9 SPUR 8 SPUR 7 SPUR 6 SPUR 5 SPUR 4 SPUR 3 SPUR 2 SPUR 1 TRUNK OUT TRUNK IN Figure 3 2 External dimensi...

Page 9: ...T 9371 FB2 6 spur enclosure 1 2 3 6 Fieldbus instruments 9377 FB R Fieldbus Barrier module 6 spur Host Control System T Fieldbus Power Supply Host Control System 1 2 3 6 T 9377 FB R Fieldbus Barrier...

Page 10: ...ditions for safe use that must be adhered to and the copy certificate supplied should be studied and understood Additionally it is recommended that a working knowledge of IEC EN 60079 14 be attained a...

Page 11: ...ut both are suitable for cables from 0 5mm2 AWG 20 up to 2 5mm2 AWG 14 On completion of installation check all blanking plugs and cable glands are tightened to ensure IP rating of the enclosure is mai...

Page 12: ...hould adopt the one that conforms to their system s normal grounding method IMPORTANT Whichever method is used the screen shield should only be grounded AT ONE END of the cable Grounding at both ends...

Page 13: ...be grounded at the Fieldbus Barrier For this arrangement insert the link as shown in Figure 4 2 Note After configuring the required grounding option tighten the screw terminals to a recommended torque...

Page 14: ...S OF A SPARE TRUNK IN CABLE MUST BE CONNECTED ONLY TO TERMINALS MARKED NC THIS ENSURES THAT THE SPARE CABLE IS NOT ELECTRICALLY CONNECTED IN PARALLEL WITH THE ACTIVE TRUNK IN OR TRUNK OUT CABLES THE C...

Page 15: ...4 4 Trunk Terminator F93 XE If the trunk is being looped onward to another enclosure then no fieldbus terminator is required but if the enclosure is the last or only enclosure on the trunk segment th...

Page 16: ...closure to allow for adjustment if a Spur Surge module is taken out of circuit inside the enclosure See Section 5 4 1 for further details Cable ferrules must be fitted to any stranded cable or screen...

Page 17: ...ide the required IP seal in accordance with gland installation instructions that there are no loose cable ends that could cause an open or short circuit that the protective trunk wiring cover is in pl...

Page 18: ...e s 9376 SP Trunk Surge module FS32 Spur Surge modules and any spur wiring All other wiring in the enclosure requires the trunk power to be isolated or a gas clearance certificate to be obtained befor...

Page 19: ...any way Do not use or attempt to repair a barrier module that has any of its pins bent or damaged because this might affect its safety and will invalidate the certification a Engage the locating guide...

Page 20: ...permit to work procedures If spur wiring is removed from a connecting plug ensure that the same polarity is observed when it is reconnected 5 4 1 Removing a Spur Surge module spur cable adjustment If...

Page 21: ...the Trunk Terminal area may be removed Refer to Section 4 2 1 for additional information about trunk wiring connections When any changes or checks have been carried out ensure there are no loose imple...

Page 22: ...nnections to the enclosure that the d c supply powering the incoming trunk is operating correctly Spur LEDs ON ON ON Green Steady Channel powering spur spur OK Green Flashing Channel powering spur but...

Page 23: ...079 1 EN 60079 7 EN 60079 11 EN 60079 18 and EN 60079 31 7 2 Installation a The installation should comply with the appropriate European national and local regulations which may include reference to t...

Page 24: ...users may have specific requirements which should also be met b Care should be taken to limit dust accumulation on the exterior of the apparatus to a depth not exceeding 5mm c If the outer enclosure o...

Page 25: ...INM 937x FB2 Px SS Rev 1 21 Barrier marking Trunk surge protector marking Terminator marking Enclosure marking Made in India Module carrier...

Page 26: ...INM 937x FB2 Px SS Rev 1 22 THIS PAGE IS LEFT INTENTIONALLY BLANK...

Page 27: ...INM 937x FB2 Px SS Rev 1 23 THIS PAGE IS LEFT INTENTIONALLY BLANK...

Page 28: ...aya Str 33 Building 4 Moscow 107076 Russia Tel 7 495 981 3770 Fax 7 495 981 3771 E mail mtlrussia eaton com SINGAPORE Cooper Crouse Hinds Pte Ltd No 2 Serangoon North Avenue 5 06 01 Fu Yu Building Sin...

Reviews: