Flexi -3G Installation & Commissioning Manual
Chapter 9. Appendices
Page 82 of 94
Document No: - 4493-CM-EN-10989402
Copyright © 2008-2009 Eaton Corporation. All Rights Reserved
ELECTRICAL & TESTING
Inspect that AC test results carried out as
per IEE Regulations – check system
logbook entry.
Y / N
Inspection of DC system installation performed,
sheet completed and signed.
Y / N
Confirm DC Bus integrity.
Y / N
Record float voltage measured at Main bus
bars.
V
Record float voltage of System displayed on
SC200 Controller.
V
Test Low Voltage Disconnect (LVD) if
applicable and ensure correct function.
Y / N
Record load current.
A
All batteries are on float charge.
Y / N
Record battery current.
A
V System I/P configuration is appropriate for and
correctly configured for the mains supply.
Y/N
V
V
Record AC supply voltages
V
Check Analogue measurements as
required in Section 8.
Y / N
Perform local alarm tests as required in
Section 8.
Y / N
Local Alarms generated and reset.
Y / N
Check Remote comms ie. Ethernet and/or
SNMP.
Y / N
DOCUMENTATION
Initial Electrical Measurement & Record
Schedule as prescribed by local regulations
Electrical Completion & Initial Inspection &
Testing Certificate as prescribed by local
regulations
Site Acceptance Certificate*
Ensure that a copy of all documentation is left within
a document holder with the equipment and other
copies are forwarded on to Eaton.
Documents to be left on site:
Any other Test Sheets
VERIFICATION & SIGN OFF
DATE:
SIGNATURE:
NAME:
COMPANY
POSITION: