Flexi -3G Installation & Commissioning Manual
Chapter 7. Installation of DC Cables
Page 68 of 94
Document No: - 4493-CM-EN-10989402
Copyright © 2008-2009 Eaton Corporation. All Rights Reserved
7.2.3. Terminate load cables
1
DC Load MCB Terminal
Screw
2
Live (L-/grey) Load Cable
3
Cable Clamp (Bus bar)
4
Return (M/blue) Load Cable 5
Cut-out Panel for DC Cable
Entry
Fig. 7-3 Connecting DC Load Cables
1.
Terminate the return (M/blue) cable connections to the common busbar using the
cable clamps provided. Tighten screws to a torque of 2.9Nm.
2.
Terminate the live (L-/grey) cable connections at the appropriate load MCBs.
Ensure that the MCB sense wires are maintained in the load termination side of
the breaker.
3.
Tighten terminal screws to a torque of 1.4Nm.
7.2.4. Refit panels (if required)
1.
If it is not required to continue the installation work then re-fit the optional DC
Distribution Cover Insulator.
Procedure complete