7
●
To connect the load with the UPS, please turn off all the loads
first, then perform the connection and finally turn on the loads
one by one.
●
No matter the UPS is connected to the utility power or not,
th
e
output of the UPS may have electricity. The parts inside
the unit may still have hazardous voltage after turning off the
UPS. To make the UPS have no output, power off the UPS,
and then disconnect the utility power supply.
●
Suggest charging the batteries for 8 hours before use. After
connection, turn the bypass breaker in the
“
ON
”
position, the
UPS will charge the batteries automatically. You can also use
the UPS immediately without charging the batteries first, but
the backup time may be less than the standard value.
●
If it is necessary to connect the inductance load such as a
monitor or a laser printer to the UPS, the start-up power
should be used for calculating the capacity of the UPS, as its
start-up power consumption is too big when it is started.
Important notes: If the UPS is used in single mode, JPI and JP2
must be connected by 10AWG(6mm
2
). If the UPS is used in
parallel mode, the Jumper between JP1 and JP2 must be removed
Input and output Terminal Block wiring diagram of 6000L(XL)/10000L(XL)