IM05805001K
27
Effective November 2003
26. LMR
Commissioning List
Read Completely Before Proceeding With Start Up
Sign-Off
Physical Inspection
Inspect for Enclosure Damage
Inspect for Component Damage within Enclosure
Controller Free of Debris (Inside and Outside Controller)
All Packing Material is Removed from Controller (i.e.- behind pressure switch)
All Components are Secure within Enclosure
All Moving Parts are Allowed to Move Freely
-Push
Buttons
-Door
Handles
-Manual
Operator
-Micro
Switch
-Contactors/Breakers
-Transfer
Switch
Wiring Inspection
Inspect all Wiring to and from Controller
Compare rating nameplates on controller and motor.
All Electrical Connections are tight
All Wiring to and from Controller is Correct
-Motor
-Utility
-Emergency Power (for FT series)
-Field Connections (Remote Starters, etc)
Immediately Before Initial Start-Up
Check Pressure Switch Connections
-Ensure Pressure Switch is connected to pump discharge
-Check for leaks from Pressure Switch to incoming sensing line.
LMR Configuration Checklist
Change Date & Time
Set Weekly Run Timer - (If required)
Set Run Period Timer
Set Acceleration Timer - (reduced voltage models only).
Set Fail to Start Timer
Set Pressure Start Point
Set Pressure Stop Point
Set Low Pressure Alarm
Set Pressure Deviation
Set Sequential Start Timer
Summary of Contents for Cutler-Hammer LMR
Page 2: ...Effective November 2003 ...
Page 6: ......
Page 21: ...IM05805001K 15 Effective November 2003 10 FIGURE 3 TYPICAL SCHEMATIC ...
Page 23: ...IM05805001K 17 Effective November 2003 13 FIGURE 5 LMR PROGRAMMING MENU ...
Page 27: ...IM05805001K 21 Effective November 2003 18 FIGURE 7 FDF SCHEMATIC ...
Page 30: ...24 IM05805001K Effective November 2003 22 FIGURE 10 FDM MEDIUM VOLTAGE DIMENSIONS ...
Page 31: ...IM05805001K 25 Effective November 2003 23 FIGURE 11 FDM SCHEMATIC ...