Eaton 93E Integrated Transformer Cabinet (ITC) Installation Manual P-164000074—Rev 3
www.eaton.com/powerquality
13. Roll the ITC to the final installation location on the right side of the UPS cabinet making sure the doors are
flush with each other.
14. Secure the ITC in position by lowering the leveling feet until the cabinet is locked in place.
15. If permanently mounting the ITC, proceed to Step 16; otherwise, proceed to Step 19.
16. Locate the two floor mounting brackets from the parts kit.
17. Using the retained cabinet mounting bolts, install the floor mounting brackets to the front and rear of the
ITC with the angle facing outward.
18. Secure the cabinet to the floor with customer-supplied hardware.
19. If installing a second ITC for dual-feed, repeat Steps 1 through 19; otherwise, proceed to Step 20. Install
the second ITC on the left side of the first ITC.
20. Proceed to paragraph 4.3.
NOTE
Use leveling feet only to lock the cabinet in place. Using the leveling feet to raise the
cabinet may result in serious injury to personnel or damage to the cabinet.